OH Consultant
← SWMS

Excavation SWMS Templates — Safe Work Method Statements for Trenching, Excavators and Earthmoving

Excavation near services, Dial-Before-You-Dig (DBYD), horizontal directional boring (HDD), trench shoring, and underground utility install SWMS. AS 5488 classification of subsurface utility information, AS/NZS 5577 location, and trench collapse controls.

⚖️WHS Regulation 2025 & Codes of Practice — legally binding from 1 July 2026 (s26A)
👷Reviewed by certified occupational health and safety professionals
🗺️State-specific variants for all 8 Australian jurisdictions

About these SWMS

Excavation and underground utilities SWMS templates cover trenching, bulk earthworks, shoring, piling, horizontal directional drilling (HDD), dewatering and excavation near live services governed by WHS Regulation 2025 Part 6.3 (excavation work) and section 291 high-risk construction work categories. Trench work deeper than 1.5 metres is HRCW under section 291(g)(i), mandating a SWMS before work commences. Templates align with the Model Code of Practice: Excavation Work, AS 5488.1 Classification of Subsurface Utility Information (SUI), AS/NZS 5577 Electricity network safety management, and Dial Before You Dig (BYDA) referral protocols. Suited to civil contractors, utility installers, plumbers, piling crews and HDD operators seeking regulator-ready documentation for trench collapse, service strike, ground instability and mobile plant interaction hazards.

What this category covers

  • ✓Trench excavation deeper than 1.5 metres with shoring and benching
  • ✓Bulk site cut and fill earthworks with mobile plant
  • ✓Hydraulic rock breaking and pneumatic ground breaking operations
  • ✓Bored and driven piling, sheet piling and trench sheeting installation
  • ✓Underpinning works adjacent to existing structures and footings
  • ✓Groundwater dewatering and trench water management systems
  • ✓Excavated soil handling, stockpiling, classification and offsite disposal
  • ✓Retaining wall construction including drainage and tie-back installation
  • ✓Horizontal directional drilling (HDD) for utility crossings
  • ✓Excavation near live underground services using DBYD/BYDA referrals
  • ✓Service location, potholing and non-destructive vacuum excavation
  • ✓Confined space entry into shafts, pits and deep excavations
CIH-reviewed SWMS library

21 SWMS in this category

21 ready-to-buy editable DOCXs · 8 state variants per product · available for instant download.

🔍

Excavation

37 SWMS

⛏️Excavation Work SWMS

Excavation for footings, services, basements, and trenching including shoring and edge protection.

$149 AUDINSTANT
Buy Excavation Work SWMS →

⛏️Bored Pier & Caisson Construction SWMS

NSW — Bored Pier & Caisson Construction. Full task scope, hazards and controls to be authored to Phase 1 standard.

$249 AUDINSTANT
Buy Bored Pier & Caisson Construction SWMS →

⛏️Bulk Earthworks SWMS

NSW — Bulk Earthworks. Full task scope, hazards and controls to be authored to Phase 1 standard.

$199 AUDINSTANT
Buy Bulk Earthworks SWMS →

⛏️Bulk Excavation — Site Cut & Fill SWMS

Bulk excavation involves large-scale earthwork for site preparation, basements, and foundations.

$149 AUDINSTANT
Buy Bulk Excavation — Site Cut & Fill SWMS →

⛏️Detailed Excavation Near Services SWMS

NSW — Detailed Excavation Near Services. Full task scope, hazards and controls to be authored to Phase 1 standard.

$299 AUDINSTANT
Buy Detailed Excavation Near Services SWMS →

⛏️Dewatering — Groundwater Management SWMS

Dewatering involves removing groundwater from excavations to allow construction work to proceed.

$99 AUDINSTANT
Buy Dewatering — Groundwater Management SWMS →

📋Excavation JSA SWMS

Covers general excavation and trenching for footings, drainage, service installation and civil works using an excavator with a support crew.…

$99 AUDINSTANT
Buy Excavation JSA SWMS →

⛏️Excavation Near Underground Services (DBYD) SWMS

SWMS template for excavation near underground services (dbyd). Covers DBYD lookup, pothole/vacuum truck, hand-dig zones. 8-state AU coverage…

$149 AUDINSTANT
Buy Excavation Near Underground Services (DBYD) SWMS →

⛏️Land Clearing & Grubbing SWMS

NSW — Land Clearing & Grubbing. Full task scope, hazards and controls to be authored to Phase 1 standard.

$149 AUDINSTANT
Buy Land Clearing & Grubbing SWMS →

⛏️Piling — Bored & Driven SWMS

Piling involves installing foundation piles by boring, driving or screwing steel, concrete or timber piles into the ground.

$199 AUDINSTANT
Buy Piling — Bored & Driven SWMS →

⛏️Retaining Wall Construction SWMS

Retaining wall construction involves excavation, foundation preparation, and construction of walls to retain soil at different levels.

$149 AUDINSTANT
Buy Retaining Wall Construction SWMS →

⛏️Rock Breaking — Hydraulic Breaker SWMS

Rock breaking using hydraulic breakers on excavators involves breaking rock formations during excavation.

$149 AUDINSTANT
Buy Rock Breaking — Hydraulic Breaker SWMS →

⛏️Rock Breaking & Ripping SWMS

NSW — Rock Breaking & Ripping. Full task scope, hazards and controls to be authored to Phase 1 standard.

$199 AUDINSTANT
Buy Rock Breaking & Ripping SWMS →

⛏️Sheet Piling / Trench Sheeting SWMS

SWMS template for sheet piling / trench sheeting. Covers Driven sheets / silent press, trench shoring. 8-state AU coverage, CIH-reviewed edi…

$149 AUDINSTANT
Buy Sheet Piling / Trench Sheeting SWMS →

⛏️Soil Compaction & Grading SWMS

NSW — Soil Compaction & Grading. Full task scope, hazards and controls to be authored to Phase 1 standard.

$149 AUDINSTANT
Buy Soil Compaction & Grading SWMS →

⛏️Soil Removal & Disposal SWMS

Soil removal involves excavating, loading, transporting and disposing of soil from construction sites. Contaminated soil (from former indust…

$99 AUDINSTANT
Buy Soil Removal & Disposal SWMS →

⛏️Trench Excavation — Shoring & Benching SWMS

Trench excavation for services involves digging narrow trenches for pipes, cables and drainage. Trenches deeper than 1.5 metres require shor…

$149 AUDINSTANT
Buy Trench Excavation — Shoring & Benching SWMS →

⛏️Underground Tank Removal SWMS

NSW — Underground Tank Removal. Full task scope, hazards and controls to be authored to Phase 1 standard.

$299 AUDINSTANT
Buy Underground Tank Removal SWMS →

⛏️Underpinning SWMS

Underpinning involves strengthening or deepening existing foundations by excavating beneath them and pouring new concrete.

$149 AUDINSTANT
Buy Underpinning SWMS →

Directional Drilling

3 SWMS

🪨Directional Drilling SWMS

Horizontal directional drilling (HDD) for utilities and civil infrastructure — pilot bore, pre-ream, pullback, bore-path surveying, service-…

$199 AUDINSTANT
Buy Directional Drilling SWMS →

🚜Horizontal Directional Boring SWMS

Horizontal directional drilling for utility installation covers entry/exit pit excavation, drill rig operation, walkover locating, mud handl…

$149 AUDINSTANT
Buy Horizontal Directional Boring SWMS →

When is a SWMS Required for Excavation and Earthmoving?

A Safe Work Method Statement is legally required under WHS Regulation 2025 Part 6.1 Division 3 before any high-risk construction work commences. Schedule 1 of the Regulation identifies the 18 categories of HRCW, and excavation and earthmoving work routinely triggers several of them at once.

The most obvious trigger is work in or near a trench or shaft with an excavated depth greater than 1.5 metres. This is the point at which trench collapse becomes reliably fatal, because the weight of soil above a worker's head is sufficient to cause compressive asphyxiation and blunt-force internal injury. Note that the 1.5 metre threshold applies to the excavated depth, not the depth at which a worker is standing — a 2 metre trench with a worker standing on backfill at 1.2 metres is still regulated as a 2 metre excavation.

Additional HRCW triggers routinely activated by excavation include: work on or near energised electrical installations (underground power cables); work on or near pressurised gas distribution mains; work on or near chemical, fuel, or refrigerant lines; work in an area that may have a contaminated or flammable atmosphere (brownfield sites, landfill cells, former service station sites); work in an area where there is any movement of powered mobile plant; work involving a confined space (deep excavations with restricted access, valve chambers, sumps); and work in or near water that involves a risk of drowning (excavations below the water table, work near rivers or stormwater).

In Victoria, the equivalent trigger is contained in Part 5.1 of the OHS Regulations 2017 and uses employer/employee terminology rather than PCBU/worker. The substantive threshold of 1.5 metres excavation depth is the same. Tasmania, Queensland, South Australia, Northern Territory, ACT, and Western Australia all follow the harmonised WHS model.

Trench Collapse — The Primary Fatal Hazard

Trench collapse is the defining hazard of excavation work. The Code of Practice: Excavation Work (Safe Work Australia, 2018) identifies unsupported excavation as a significant cause of fatality in Australian construction, and state regulator investigations routinely find that fatal collapses occurred in trenches that had no shoring, no battering, and no benching.

The physics are unforgiving. One cubic metre of dry soil weighs approximately 1.5 tonnes; saturated clay or silty soils can exceed 1.9 tonnes per cubic metre. A worker buried to chest height under collapsed soil cannot expand their ribcage against that weight, and suffocation occurs within three to five minutes. Even partial burial from knee height can cause crush injuries to pelvis and lower limbs that require immediate technical rescue. Because the weight of soil progressively compresses the worker's chest, the time between collapse and cardiac arrest is often shorter than the time required for a rescue team to arrive on site.

Ground conditions change without visible warning. A trench that stood open for two days may collapse on day three because of overnight rain, vibration from nearby plant, surcharge loading from spoil piled too close to the edge, or simple relaxation of the soil mass. The Code of Practice requires that excavations deeper than 1.5 metres must be battered, benched, or shored unless a competent person has assessed the soil and certified that the walls are stable for the duration of the work. 'We didn't think it would collapse' is not a defence — the regulator expects ground support or certified stability, full stop.

Shoring systems used in Australia include hydraulic aluminium shores, trench shields (sometimes called trench boxes), timber shoring, steel sheet piling for deeper or waterlogged excavations, and soldier pile and lagging systems for larger civil works. Each system has load ratings and installation requirements that must be followed in accordance with the manufacturer's instructions and, where required, a geotechnical engineer's design.

Underground Service Strikes

Underground service strikes are the second category of fatal excavation hazards. Striking a live 11 kV or 33 kV underground cable with an excavator bucket can electrocute the operator through the machine, eject molten copper and vaporised soil at the strike point, and cause explosive failure that injures ground crew within several metres. Striking a pressurised gas main can release natural gas or LPG that ignites on contact with the excavator exhaust or any ignition source on site, causing fire and explosion. Striking a high-pressure water or wastewater main can erode surrounding soil and destabilise the excavation, precipitating collapse on workers inside.

The primary control is a Before You Dig Australia (BYDA) plan obtained before any ground disturbance. BYDA is a free service that coordinates with asset owners — electricity distributors, gas networks, water authorities, telecommunications carriers, and local councils — to provide plans of known underground services at the excavation location. Plans must be obtained within the previous 30 days because networks are extended and modified continuously. A plan obtained six months ago may no longer accurately reflect what is in the ground.

BYDA plans do not eliminate the need for physical verification. Plans have a stated tolerance (typically ±500 mm to ±1 metre depending on the asset owner) and may be inaccurate due to historic survey errors, undocumented relocations, and private services that were never registered. The Code of Practice: Excavation Work requires that mechanical excavation within the plan tolerance zone of any underground service must be preceded by hand-digging, hydro-excavation (vacuum truck), or cable-locating using an electromagnetic locator. This process is sometimes called 'potholing' and is mandatory for any excavation near known services.

A SWMS for excavation must document the BYDA process, the physical verification method, the exclusion zones around located services, and the escalation procedure if an unknown service is encountered during digging. The SWMS should name the asset owner emergency contact for each category of service and specify the stop-work threshold that triggers notification.

Powered Mobile Plant and Plant-Pedestrian Interaction

Earthmoving sites operate multiple powered mobile plant simultaneously: excavators, wheel loaders, skid steer loaders, dump trucks, articulated dump trucks, graders, rollers, scrapers, and dozers. Plant-pedestrian interaction — where a worker on foot is struck, crushed, or run over by moving plant — is a persistent cause of fatality and serious injury on civil sites.

The hierarchy of controls for plant-pedestrian risk begins with elimination: physically separating workers from plant operating areas using exclusion zones, fencing, or designated pedestrian-only routes. Where separation is not reasonably practicable, the next control is ensuring that every operator has direct line-of-sight to any worker within the plant's operating envelope, supplemented by 360 degree camera systems, proximity sensors, and RFID-based proximity warning systems for machines with known blind spots.

All plant operators must hold the relevant High Risk Work Licence where required, or demonstrate verifiable competency where a licence is not mandatory. The unit of competency for excavator operators is RIIMPO320F (Conduct civil construction excavator operations), which is the current national code. Older codes such as RIIMPO320E are superseded and should not be referenced in current SWMS. Wheel loaders, dozers, graders, and scrapers each have their own RII competency codes.

The SWMS must document the traffic management plan for the site — the routes that plant will take, the locations where workers will be on foot, the spotters and traffic controllers who will manage interactions, and the communication protocol (two-way radio, hand signals, horn signals) that will coordinate plant movements with worker activity. For larger civil sites, the traffic management plan should be a separate controlled document referenced from the SWMS.

Hierarchy of Controls for Excavation Work

The WHS Regulation 2025 requires that risks be managed in accordance with the hierarchy of controls, from most effective (elimination) to least effective (personal protective equipment). For excavation and earthmoving, the hierarchy applied to the critical hazards is as follows.

Elimination: wherever reasonably practicable, eliminate the need for workers to enter excavations at all. This can be achieved by specifying trenchless methods (horizontal directional drilling, microtunnelling, pipe bursting) for service installation; by using remote-operated or long-reach excavators for the final trim rather than hand-finishing; and by designing drainage and services to run in shallow trenches where workers can complete connections from above.

Substitution: where excavation cannot be eliminated, substitute hand-digging or mechanical excavation with vacuum excavation (hydro-excavation) in the vicinity of underground services. Vacuum excavation eliminates the risk of cable or pipe strike from a tool or bucket and is now the standard method for exposing services in tolerance zones.

Isolation: isolate workers from unstable ground by using trench shields, hydraulic shoring, or steel sheet piling. Isolate workers from moving plant by establishing exclusion zones marked by physical barriers and signage. Isolate the excavation from surface water by using bunding, diversions, and pump sumps to prevent inundation.

Engineering controls: specify battering of trench walls to the natural angle of repose for the soil type (typically 45 degrees for firm clay, 34 degrees for loose sand); specify benching for excavations deeper than 3 metres; design ground support systems and have the design certified by a Chartered Professional Engineer where required; use geotechnical assessment to determine whether the ground can stand unsupported for the duration of the work.

Administrative controls: obtain BYDA plans before any ground disturbance; conduct daily pre-start inspections of all excavations and ground support before entry; implement a permit-to-enter system for excavations deeper than 2 metres; train all workers in excavation hazards (unit of competency RIICWD503D); implement atmospheric monitoring for deep excavations or excavations in contaminated ground; establish and communicate emergency rescue procedures.

Personal protective equipment: high-visibility clothing to AS/NZS 4602.1; safety helmet to AS/NZS 1801; steel-capped safety boots to AS/NZS 2210.3; eye protection to AS/NZS 1337; hearing protection to AS/NZS 1270 when working near plant; gas detectors (four-gas) for deep excavations or contaminated ground.

Training and Competency Requirements

Every worker carrying out excavation or earthmoving work must hold the General Construction Induction (White Card) under unit of competency CPCCWHS1001. This is the minimum prerequisite for any work on a construction site in Australia. Workers also require training in the specific hazards of the work they will carry out, delivered before the work commences and documented on the worker sign-on sheet for the SWMS.

Excavator operators should hold RIIMPO320F (Conduct civil construction excavator operations). Wheel loader operators should hold the relevant RII unit for wheeled or tracked loaders. Dozer operators should hold RIIMPO318F or equivalent. Roller operators should hold RIIMPO317F. Dump truck operators on haul roads should hold RIIMPO321F. Where the plant is used on a public road, the operator must also hold an appropriate driver licence class issued by the relevant state road authority.

Forklifts and order pickers require a TLILIC0003 or TLILIC0004 High Risk Work Licence depending on the specific machine. Elevated work platforms with a boom length over 11 metres require a WP class HRWL. Dogging and rigging on civil sites involving crane operations require the relevant DG or RB/RI/RA HRWL.

Workers entering deep excavations that meet the definition of a confined space must be trained in confined space entry to AS 2865:2009 (note that AS 2865 explicitly excludes trenching and general excavation work from its scope, but applies where the excavation meets the confined space definition due to restricted access, atmospheric hazards, or limited egress). Confined space training is delivered as unit MSMWHS217 (Gas test atmospheres) combined with MSMPER205 (Enter confined space) or equivalent industry training.

Codes of Practice and Australian Standards

The following regulatory instruments apply to excavation and earthmoving SWMS and must be referenced where relevant: Code of Practice: Excavation Work (Safe Work Australia, 2018), which is the primary practical guidance document for excavation in the model WHS jurisdictions; Code of Practice: Construction Work (Safe Work Australia, 2018); Code of Practice: Managing the Risks of Plant in the Workplace (Safe Work Australia, 2020); Code of Practice: Confined Spaces (Safe Work Australia, 2020); and Code of Practice: Managing Electrical Risks in the Workplace (2022) where underground electrical services may be encountered.

In Victoria, the equivalent documents are Compliance Codes rather than Codes of Practice, issued by WorkSafe Victoria. Victoria uses the Compliance Code: Excavation and the Compliance Code: Confined Spaces. The legal status differs slightly — Victorian Compliance Codes provide practical guidance on compliance with the OHS Act 2004 and OHS Regulations 2017, but Codes of Practice in WHS jurisdictions are admissible in proceedings as evidence of what is known about a hazard.

Relevant Australian Standards include AS 2187.2 (Explosives — Use of explosives, for blasting operations); AS/NZS 4576 (Guidelines for scaffolding); AS 2865:2009 (Confined spaces, where the excavation meets the confined space definition); AS 1742.3 (Manual of uniform traffic control devices — Traffic control for works on roads, for civil sites interacting with public roads); and AS 4970 (Protection of trees on development sites) where excavation occurs near trees protected under planning instruments.

Each template in this guide references the specific standards applicable to that activity.

Emergency Rescue and Notifiable Incidents

The Code of Practice: Excavation Work requires that every excavation SWMS include an emergency rescue plan capable of retrieving an injured or buried worker within the shortest possible timeframe. Because compressive asphyxiation from trench burial can cause death within three to five minutes, emergency services (000) will in most cases not arrive in time to rescue a worker who has been fully buried. The rescue plan must therefore provide for immediate on-site response using the plant and equipment already present.

On-site rescue equipment for excavation work should include: a second competent excavator operator and machine capable of clearing spoil quickly without further endangering the buried worker; shovels and hand tools for the final exposure once the victim is located; a trauma first aid kit including oxygen, trauma dressings, and a spinal board; and a means of immediate communication to emergency services. All workers must be briefed on the rescue procedure before entry, and the site supervisor must confirm that the rescue equipment is present and operational at the start of every shift.

Under WHS Act 2011 section 38, a notifiable incident must be reported to the regulator as soon as practicable. A notifiable incident includes any death at a workplace; any serious injury or illness requiring hospital admission; and any dangerous incident, which explicitly includes the collapse or partial collapse of an excavation. This means that even a trench collapse with no injury must be notified to the regulator. The site must be preserved in the state it was in immediately after the incident until an inspector authorises disturbance, unless preservation would create further risk.

Industrial manslaughter is now an offence in every Australian state, territory, and at the Commonwealth level. The maximum penalties for industrial manslaughter range from 20 years imprisonment to life imprisonment depending on the jurisdiction, and corporate fines can exceed $18 million. A SWMS that specifies shoring which was not installed, or that identifies a rescue plan which was not rehearsed, becomes key evidence in any such prosecution.

Applicable standards & regulations

Model Code of Practice: Excavation Work (Safe Work Australia)
Sets PCBU duties for ground assessment, shoring/benching, edge protection, atmospheric testing and emergency rescue planning for all excavations regardless of depth.
AS 5488.1:2019 Classification of Subsurface Utility Information (SUI)
Defines Quality Level A–D for underground service information; SWMS must reference SUI quality before mechanical excavation near services.
AS/NZS 4576:1995 Guidelines for Scaffolding (trench shoring application) and WHS Regulation 2025 Part 6.3 Excavation Work
Regulation 304–306 mandate ground stability assessment, shoring design and safe means of entry/exit for all trenches over 1.5 metres.
AS/NZS 3000:2018 Wiring Rules and AS/NZS 5577:2013 Electricity Network Safety Management
Governs safe approach distances and isolation requirements when excavating near underground electrical cables and network assets.

Frequently asked questions

Is trench excavation deeper than 1.5 metres high-risk construction work in Australia?

Yes. Under WHS Regulation 2025 section 291, any work in or near a trench or shaft with an excavated depth greater than 1.5 metres is classified as high-risk construction work (HRCW). A SWMS must be prepared, available at the workplace, and complied with before work commences. The Model Code of Practice: Excavation Work also triggers ground assessment, shoring or benching, and rescue planning duties regardless of whether the trench reaches the 1.5 metre threshold.

Do I need a separate SWMS for HDD and open-cut excavation on the same job?

Yes — each high-risk activity requires its own task-specific SWMS because the hazards, controls and competencies differ. Horizontal directional drilling introduces inadvertent returns, strike-alert systems and pressurised fluid hazards under section 291(o) (movement of powered mobile plant), while open-cut excavation focuses on trench collapse, edge stability and service strike. Combining them into one document typically fails regulator review because controls cannot be traced to specific tasks as required by section 299.

What does DBYD or BYDA require before I start excavating near underground services?

Before Mechanical Excavation, the PCBU must lodge a Before You Dig Australia (BYDA, formerly DBYD) referral to obtain asset plans from utility owners. The Model Code of Practice: Excavation Work requires plans to be reviewed, services potholed using non-destructive methods (vacuum or hand excavation), and physically marked before mechanical plant is used. AS 5488.1 Quality Level B or A information is generally required within 500 mm of identified services to satisfy the duty to eliminate or minimise service strike risk.

What is the difference between shoring, benching and battering in trench work?

Shoring uses engineered supports (hydraulic shores, trench shields, sheet piles) to prevent collapse; benching cuts horizontal steps into trench walls; battering slopes the walls back to a safe angle of repose. The Model Code of Practice: Excavation Work requires a competent person to assess ground conditions and select an appropriate method. For trenches over 1.5 metres, an engineered shoring design under AS 4678 principles is generally required unless soil is stable rock or battered to the natural angle of repose.

Are excavation SWMS the same across all Australian states and territories?

The technical content is largely harmonised because WHS Regulation 2025, section 291 HRCW categories, and the Model Code of Practice: Excavation Work apply nationally — except in Victoria, which operates under OHS Regulations 2017 with equivalent High Risk Construction Work provisions. Western Australia adopted the model WHS framework in 2022. State-specific differences typically relate to notification thresholds, regulator details and dial-before-you-dig referral processes, which the SWMS should reference based on the jurisdiction of the work site.

At what depth does an excavation require a SWMS?

Under WHS Regulation 2025 Schedule 1, a Safe Work Method Statement is required for any work in or near a trench or shaft with an excavated depth greater than 1.5 metres. The 1.5 metre threshold applies to the excavated depth, not the working depth of a person inside the trench. A SWMS may also be required at shallower depths if other HRCW categories are triggered — for example, work near energised underground cables, work on or near pressurised gas mains, or work in a contaminated or flammable atmosphere. In Victoria, the equivalent requirement is in OHS Regulations 2017 Part 5.1 with the same 1.5 metre threshold.

Do I need shoring for every trench deeper than 1.5 metres?

The Code of Practice: Excavation Work requires that excavations deeper than 1.5 metres must be battered, benched, or shored unless a competent person has assessed the ground and certified that the walls are stable for the duration of the work. In practice, most soils in Australia will not stand vertically for the time required to install services, so ground support is the default expectation. A geotechnical assessment by a Chartered Professional Engineer is the only basis for working in an unsupported excavation deeper than 1.5 metres, and the assessment must be documented in the SWMS.

What is BYDA and is it mandatory?

Before You Dig Australia (BYDA, previously Dial Before You Dig) is the national underground service location service. Plans obtained via BYDA show the location of registered underground services — electricity, gas, water, sewerage, telecommunications, and others — at the excavation site. While BYDA itself is not directly mandated by legislation, the Code of Practice: Excavation Work and equivalent documents in each jurisdiction require that the location of underground services must be established before any ground disturbance. A current BYDA plan (obtained within the last 30 days) is the standard way to meet this requirement, and a SWMS that does not document a BYDA check will not satisfy a regulator or principal contractor.

What licence is needed to operate an excavator?

Excavator operators on civil and construction sites should hold the national unit of competency RIIMPO320F (Conduct civil construction excavator operations). This is not a High Risk Work Licence (HRWL) under the WHS Regulation — it is a Statement of Attainment issued by a Registered Training Organisation. Operators must also hold the General Construction Induction (White Card, CPCCWHS1001) for any work on a construction site. Where the excavator is driven on a public road, the operator must hold an appropriate driver licence class. Principal contractors routinely require verification of competency through the operator's Statement of Attainment or a recognised VOC (Verification of Competency) document.

Does the SWMS need to include a rescue plan?

Yes. The Code of Practice: Excavation Work requires that every excavation SWMS include an emergency rescue plan capable of retrieving an injured or buried worker. Because compressive asphyxiation from trench burial can cause death within three to five minutes, the rescue plan must provide for immediate on-site response rather than relying solely on emergency services response. The plan should specify the rescue equipment available on site, the personnel trained to use it, the communication protocol, and the method of summoning additional emergency response. A SWMS that states only 'call 000' as the emergency procedure for a trench collapse does not satisfy the Code.

Excavation & Trenching SWMS

Editable DOCX templates, 8 state variants per product, CIH-reviewed.

Browse all SWMS