Excavation & Underground Utilities SWMS Templates
Excavation near services, Dial-Before-You-Dig (DBYD), horizontal directional boring (HDD), trench shoring, and underground utility install SWMS. AS 5488 classification of subsurface utility information, AS/NZS 5577 location, and HRCW Cat 7 trench collapse.
About these SWMS
Excavation and underground utilities SWMS templates cover trenching, bulk earthworks, shoring, piling, horizontal directional drilling (HDD), dewatering and excavation near live services governed by WHS Regulation 2025 Part 6.3 (excavation work) and Schedule 3 high-risk construction work categories. Trench work deeper than 1.5 metres is HRCW under WHS Reg 291, mandating a SWMS before work commences. Templates align with the Model Code of Practice: Excavation Work, AS 5488.1 Classification of Subsurface Utility Information (SUI), AS/NZS 5577 Electricity network safety management, and Dial Before You Dig (BYDA) referral protocols. Suited to civil contractors, utility installers, plumbers, piling crews and HDD operators seeking regulator-ready documentation for trench collapse, service strike, ground instability and mobile plant interaction hazards.
What this category covers
- βTrench excavation deeper than 1.5 metres with shoring and benching
- βBulk site cut and fill earthworks with mobile plant
- βHydraulic rock breaking and pneumatic ground breaking operations
- βBored and driven piling, sheet piling and trench sheeting installation
- βUnderpinning works adjacent to existing structures and footings
- βGroundwater dewatering and trench water management systems
- βExcavated soil handling, stockpiling, classification and offsite disposal
- βRetaining wall construction including drainage and tie-back installation
- βHorizontal directional drilling (HDD) for utility crossings
- βExcavation near live underground services using DBYD/BYDA referrals
- βService location, potholing and non-destructive vacuum excavation
- βConfined space entry into shafts, pits and deep excavations
13 SWMS in this category
13 ready-to-buy editable DOCXs Β· 8 state variants per product Β· delivered within 24 hours of payment.
Excavation
21 SWMSβοΈExcavation SWMS
Excavation for footings, services, basements, and trenching including shoring and edge protection.
βοΈBulk Excavation β Site Cut & Fill SWMS
Bulk excavation involves large-scale earthwork for site preparation, basements, and foundations.
βοΈDewatering β Groundwater Management SWMS
Dewatering involves removing groundwater from excavations to allow construction work to proceed.
βοΈExcavation Near Underground Services (DBYD) SWMS
SWMS template for excavation near underground services (dbyd). Covers DBYD lookup, pothole/vacuum truck, hand-dig zones. 8-state AU coverageβ¦
βοΈPiling β Bored & Driven SWMS
Piling involves installing foundation piles by boring, driving or screwing steel, concrete or timber piles into the ground.
βοΈRetaining Wall Construction SWMS
Retaining wall construction involves excavation, foundation preparation, and construction of walls to retain soil at different levels.
βοΈRock Breaking β Hydraulic Breaker SWMS
Rock breaking using hydraulic breakers on excavators involves breaking rock formations during excavation.
βοΈSheet Piling / Trench Sheeting SWMS
SWMS template for sheet piling / trench sheeting. Covers Driven sheets / silent press, trench shoring, HRCW Cat 6.. 8-state AU coverage, CIHβ¦
βοΈSoil Removal & Disposal SWMS
Soil removal involves excavating, loading, transporting and disposing of soil from construction sites. Contaminated soil (from former industβ¦
βοΈTrench Excavation β Shoring & Benching SWMS
Trench excavation for services involves digging narrow trenches for pipes, cables and drainage. Trenches deeper than 1.5 metres require shorβ¦
βοΈUnderpinning SWMS
Underpinning involves strengthening or deepening existing foundations by excavating beneath them and pouring new concrete.
Directional Drilling
3 SWMSπͺ¨Directional Drilling SWMS
Horizontal directional drilling (HDD) for utilities and civil infrastructure β pilot bore, pre-ream, pullback, bore-path surveying, service-β¦
πHorizontal Directional Boring SWMS
Horizontal directional drilling for utility installation covers entry/exit pit excavation, drill rig operation, walkover locating, mud handlβ¦
Applicable standards & regulations
Frequently asked questions
Is trench excavation deeper than 1.5 metres high-risk construction work in Australia?
Yes. Under WHS Regulation 2025 Schedule 3 and Regulation 291, any work in or near a trench or shaft with an excavated depth greater than 1.5 metres is classified as high-risk construction work (HRCW). A SWMS must be prepared, available at the workplace, and complied with before work commences. The Model Code of Practice: Excavation Work also triggers ground assessment, shoring or benching, and rescue planning duties regardless of whether the trench reaches the 1.5 metre threshold.
Do I need a separate SWMS for HDD and open-cut excavation on the same job?
Yes β each high-risk activity requires its own task-specific SWMS because the hazards, controls and competencies differ. Horizontal directional drilling introduces inadvertent returns, strike-alert systems and pressurised fluid hazards under WHS Reg Schedule 3 Category 13 (powered mobile plant), while open-cut excavation focuses on trench collapse, edge stability and service strike. Combining them into one document typically fails regulator review because controls cannot be traced to specific tasks as required by Regulation 299.
What does DBYD or BYDA require before I start excavating near underground services?
Before Mechanical Excavation, the PCBU must lodge a Before You Dig Australia (BYDA, formerly DBYD) referral to obtain asset plans from utility owners. The Model Code of Practice: Excavation Work requires plans to be reviewed, services potholed using non-destructive methods (vacuum or hand excavation), and physically marked before mechanical plant is used. AS 5488.1 Quality Level B or A information is generally required within 500 mm of identified services to satisfy the duty to eliminate or minimise service strike risk.
What is the difference between shoring, benching and battering in trench work?
Shoring uses engineered supports (hydraulic shores, trench shields, sheet piles) to prevent collapse; benching cuts horizontal steps into trench walls; battering slopes the walls back to a safe angle of repose. The Model Code of Practice: Excavation Work requires a competent person to assess ground conditions and select an appropriate method. For trenches over 1.5 metres, an engineered shoring design under AS 4678 principles is generally required unless soil is stable rock or battered to the natural angle of repose.
Are excavation SWMS the same across all Australian states and territories?
The technical content is largely harmonised because WHS Regulation 2025, Schedule 3 HRCW categories, and the Model Code of Practice: Excavation Work apply nationally β except in Victoria, which operates under OHS Regulations 2017 with equivalent High Risk Construction Work provisions. Western Australia adopted the model WHS framework in 2022. State-specific differences typically relate to notification thresholds, regulator details and dial-before-you-dig referral processes, which the SWMS should reference based on the jurisdiction of the work site.
Excavation & Underground Utilities SWMS
Editable DOCX templates, 8 state variants per product, CIH-reviewed.
Browse all SWMS