OH Consultant
← All SWMS Documents
πŸ—οΈ

Footing & Foundation Concreting SWMS

NSW β€” Footing & Foundation Concreting. Full task scope, hazards and controls to be authored to Phase 1 standard.

βš–οΈWHS Regulation 2025 & Codes of Practice β€” legally binding from 1 July 2026 (s26A)
πŸ‘·Reviewed by certified occupational health and safety professionals
πŸ—ΊοΈState-specific variants for all 8 Australian jurisdictions
$199 AUDβœ“ Instant Download Available

SWMS variants reference your state’s WHS legislation. Instant download after payment.

Footing and foundation concreting is the excavation, reinforcement and pouring of footings, pad and strip foundations. It is high risk construction work under the WHS Regulation because the footing excavation can exceed 1.5 m in depth, temporary support may be required to prevent the excavation collapsing, and the work is carried out with the movement of powered mobile plant β€” excavators, pumps and agitators (s291), so a SWMS is mandatory (s299). The central hazard is the plant-and-excavation interface: an excavator can strike a worker or roll over at the excavation edge, and the excavation wall can collapse where it is dug in unstable soil without battering or shoring. Where the excavation passes 1.5 m the collapse risk is acute and a person in an unsupported trench cannot self-rescue. Layered on are the concrete-material hazards (alkaline burns at pH 12-13, spatter to the eyes), formwork and reinforcement handling including impalement on projecting starter bars during a fall, and weather effects on the pour. The SWMS controls the excavation support, services location before digging, plant separation, reinforcement capping and concrete-contact PPE. It supports the engineered footing design to AS 3600, AS 2870 and AS 3798 and does not replace the engineer's specification. It is supplied in eight jurisdiction editions, each citing its own Act, Regulation and regulator.

Hazards identified

8 hazards covered, sorted by priority.

Excavation or footing-trench wall collapse in unstable soil without battering or shoringHIGH

Crush fatality or burial of a worker in the excavation (central HRCW)

Excavator strike on workers in and around the footing excavationHIGH

Struck-by or crush fatality

Excavator or plant rollover at the excavation edgeHIGH

Crush fatality and plant falling into the excavation

Failure of temporary support (shoring/bracing) holding the excavationHIGH

Sudden collapse onto workers placing steel or concrete

Underground-services strike during footing excavationHIGH

Electrocution, gas release or flooding

Impalement on projecting starter bars during a fall into the excavationHIGH

Penetrating injury from uncapped reinforcement

Skin and eye burns from wet concrete (pH 12-13) during the pourMEDIUM

Alkaline chemical burns to skin and cornea

Rain or wind during the pour affecting the excavation and boom pumpMEDIUM

Wall softening/collapse or loss of pump control

Control measures

Hierarchy-of-controls order: elimination β†’ substitution β†’ isolation β†’ engineering β†’ administrative β†’ PPE.

  1. 1Elimination β€” Use screw piles or precast footing systems where the design allows so deep open excavation is avoided
  2. 2Substitution β€” Substitute a trench shield or battered excavation for an unsupported vertical face, and pump placement for barrowing in the excavation
  3. 3Engineering β€” Batter the excavation to the soil class where it exceeds 1.5 m (Type A 0.75H:1V, Type B 1H:1V, Type C 1.5H:1V) or shore per AS 4744/AS 5047
  4. 4Engineering β€” Keep spoil, plant and materials set back from the excavation edge, and cap all projecting reinforcement
  5. 5Engineering β€” Positive services location β€” dial-before-you-dig within 30 days and non-destructive digging of services within 1.5 m β€” before machine excavation
  6. 6Administrative β€” Soil classification by a competent person, a permit to enter, and inspection of the excavation and supports each shift and after rain
  7. 7Administrative β€” Plant traffic-management plan with spotters separating the excavator from workers, and no entry to an unsupported excavation over 1.5 m
  8. 8Administrative β€” Pre-pour inspection sign-off and a weather plan for the pour
  9. 9PPE β€” Alkali-resistant gloves and gum boots for the pour crew, plus eye protection against spatter
  10. 10PPE β€” Type 1 hard hat, high-visibility clothing and steel-toe boots for all excavation and pour work

Applicable Codes of Practice

Excavation Work Code of Practiceβš– Legally binding Β· 1 Jul 2026

Central code for excavation collapse prevention and temporary support

Concrete and Concreting Work Code of Practiceβš– Legally binding Β· 1 Jul 2026

Duties for the concrete placement

Managing the Risks of Plant in the Workplace Code of Practiceβš– Legally binding Β· 1 Jul 2026

Duties for excavators and powered mobile plant

Construction Work Code of Practiceβš– Legally binding Β· 1 Jul 2026

General construction duties and SWMS requirements

AS 3600 Concrete structures

Structural concrete design and construction reference

AS 2870 Residential slabs and footings

Reference for residential footing design

AS 3798 Earthworks for commercial and residential developments

Reference for the earthworks and excavation

High-Risk Construction Work triggered

s291(e)
Involves structural alterations or repairs that require temporary support to prevent collapse

Temporary shoring or bracing is required to prevent the footing excavation collapsing.

s291(g)
Is carried out in or near a shaft or trench deeper than 1.5 metres, or a tunnel

Footing excavations routinely exceed 1.5 m in depth.

s291(o)
Is carried out in an area at a workplace in which there is any movement of powered mobile plant

Excavators, pumps and agitators move through the work area.

Legal consequence

Who this is for

  • β†’Residential builders pouring slabs and footings
  • β†’Commercial concrete contractors
  • β†’Civil contractors with footing scope
  • β†’Excavation contractors with concrete-pour scope
  • β†’Site supervisors and competent persons inspecting excavations

What you receive

  • βœ“Editable DOCX template β€” Microsoft Word compatible
  • βœ“State-specific WHS legislation schedule (NSW/VIC/QLD/SA/WA/TAS/NT/ACT)
  • βœ“Hazard register with risk ratings + hierarchy-of-control mapping
  • βœ“Worker sign-on register, pre-start checklist, and incident escalation flow

Worked example

At 7:00 am a crew from Cornerstone Foundations begins a strip footing that will run 1.8 m deep. Because it passes 1.5 m, the supervisor treats collapse as the defining risk: the walls are battered to the classified soil type, and where the boundary is tight a shield is set in before anyone enters. The dial-before-you-dig plans are current and a comms conduit crossing the line is exposed by non-destructive digging and protected. Spoil is placed well back so it cannot surcharge the wall, and the starter bars already tied are capped so no one can be impaled if they slip. A spotter keeps the excavator clear of the crew as it trims the base, using call-acknowledge-approach. When the reinforcement is inspected and signed, the boom pump β€” set on proven ground with pads deployed β€” places the footing while the crew work in gloves and gum boots to avoid concrete burns. A brief shower passes; the competent person re-inspects the batter before work resumes because wet soil loses strength. The footing is closed out with every hold point signed.

Related legislation

  • WHS Act 2011 (model)
  • WHS Regulation 2025
  • Excavation Work Code of Practice
  • AS 2870 Residential slabs and footings

Frequently asked questions

Is footing and foundation concreting high risk construction work?

Yes, and usually on three counts at once. Footing excavations routinely pass 1.5 metres, which is work in or near a trench with an excavated depth greater than 1.5 metres under section 291(g) of the WHS Regulation. Where shoring or bracing is needed to stop the excavation collapsing, section 291(e) applies. Excavators, pumps and agitators moving through the work area engage section 291(o). Any one of those brings section 299 into effect, so the SWMS must be prepared in consultation with the crew before work starts, signed, and kept on site. The document is supplied in eight jurisdiction editions, each citing its own Act, Regulation and regulator.

Does this cover the excavation, or only the concrete pour?

Both, because on a footing the two cannot be separated β€” the crew that digs it is often the crew standing in it. Scope runs from services location and excavation through temporary support, reinforcement fixing and formwork to the pour itself and the pre-pour hold points. Services location is treated as a sequence, not a phone call: a current dial-before-you-dig referral, then non-destructive digging to physically expose anything within 1.5 metres of the excavation line before a machine bucket goes near it. Live electrical, gas and communications assets are each carried as identified hazards with their own controls.

Do I have to shore the footing trench, or can I batter it?

Either, provided it is matched to the soil a competent person has actually classified. The document sets batter angles by soil type β€” 0.75H:1V for Type A, 1H:1V for Type B and 1.5H:1V for Type C β€” or shoring designed to AS 4744 and AS 5047 where the boundary is too tight to batter. The rule that goes with it is absolute: nobody enters an unsupported excavation deeper than 1.5 metres. Excavation and supports are inspected each shift and again after rain, because wet soil loses strength and a face that stood yesterday can run this morning. Spoil and plant stay set back from the edge.

How do you stop someone being impaled on starter bars?

By capping every projecting bar as soon as it is tied, not before the inspection walk. Starter bars are the hazard people underestimate on a footing: a worker who slips at the edge falls a short distance onto vertical steel, and a fall that would otherwise cause a sprain becomes a penetrating chest or abdominal injury. The control requires engineered impalement caps rather than a bent offcut or a plastic mushroom cap not rated for the purpose. It works alongside the edge controls β€” spoil set back, access kept clear, and no unnecessary traffic along the trench lip while reinforcement is standing.

Does this replace the engineer's footing design?

No. It supports work engineered to AS 3600, AS 2870 and AS 3798; it does not replace the engineer's specification, the soil classification or the pre-pour inspection sign-off. What you receive is an editable Microsoft Word document, bought once, with the hazard register and risk ratings, the full hierarchy-of-control set, hold points, a worker sign-on and consultation record, and the legislation schedule for your state. Fill in the actual soil class, the actual depth and the actual plant before the pre-start, then keep it live β€” the competent person's re-inspection after rain gets recorded on it, not in someone's memory.

What's in this SWMS

Document details

Regulation
Work Health and Safety Regulation 2025 (NSW), Section 291 β€” High Risk Construction Work
HRCW Category
s. 291(g) β€” Work in or near a shaft or trench >1.5 m or a tunnel; s. 291(o) β€” Work where there is movement of powered mobile plant
Hazards Identified
8 hazards with controls
Format
Editable DOCX (Microsoft Word)
Author
Certified Industrial Hygienist (CIH)
Delivery
Instant download after payment
CIH-reviewed SWMS Β· from $99 Β· instant download

Related SWMS templates

πŸ—οΈConcrete Floor Surfacing & Grinding SWMS

NSW β€” Concrete Floor Surfacing & Grinding. Full task scope, hazards and controls to be authored to Phase 1 sta…

$199 AUDBuy β†’

πŸ—οΈConcrete Mud-Jacking & Slabjacking SWMS

NSW β€” Concrete Mud-Jacking & Slabjacking. Full task scope, hazards and controls to be authored to Phase 1 stan…

$149 AUDBuy β†’

πŸ—οΈConcrete Pouring & Placement SWMS

NSW β€” Concrete Pouring & Placement. Full task scope, hazards and controls to be authored to Phase 1 standard.

$199 AUDBuy β†’

πŸ—οΈPoured Concrete Retaining Wall SWMS

NSW β€” Poured Concrete Retaining Wall. Full task scope, hazards and controls to be authored to Phase 1 standard…

$199 AUDBuy β†’

πŸ—οΈPrestressed Concrete Beam Installation SWMS

NSW β€” Prestressed Concrete Beam Installation. Full task scope, hazards and controls to be authored to Phase 1 …

$249 AUDBuy β†’

πŸ—οΈReinforcement Steel Fixing SWMS

NSW β€” Reinforcement Steel Fixing. Full task scope, hazards and controls to be authored to Phase 1 standard.

$149 AUDBuy β†’