Concreting & Formwork SWMS Templates
Slab pours, formwork erection and stripping, post-tensioning, shotcrete, polished concrete, decorative finishes, and precast tilt-up panel SWMS. AS 3600 concrete structures, AS 3610 formwork, and WHS Regulation 2025 HRCW where falls or structural collapse risks apply.
About these SWMS
Concreting and formwork SWMS templates cover the full sequence of structural and decorative concrete work on Australian construction sites — from rebar fixing and formwork erection through to slab pours, concrete pumping, post-tensioning, tilt-up panel erection, cutting, grinding, polishing and shotcrete application. Each template aligns with WHS Regulation 2025 (including Part 6.3 high risk construction work duties), AS 3600 Concrete Structures, AS 3610 Formwork for Concrete, and the model Code of Practice: Construction Work. Where falls over 2 metres, structural alterations, tilt-up or precast elements, or hazardous chemical exposures are present, HRCW SWMS obligations are triggered before work commences.
What this category covers
- ✓Slab on ground and suspended slab concrete pours
- ✓Formwork erection, bracing, stripping and back-propping
- ✓Concrete line and boom pump placement operations
- ✓Post-tensioning cable installation, stressing and de-tensioning
- ✓Tilt-up and precast panel lifting, bracing and erection
- ✓Rebar cutting, bending, tying and cage installation
- ✓Concrete cutting, sawing, coring and scanning prior to penetration
- ✓Concrete grinding, polishing and decorative surface finishing
- ✓Float, trowel and broom finishing of fresh concrete
- ✓Shotcrete spraying for retention walls and structural applications
- ✓Curing compound and sealer application with hazardous chemicals
- ✓Mobile plant operation including concrete agitators and pumps
32 SWMS in this category
32 ready-to-buy editable DOCXs · 8 state variants per product · delivered within 24 hours of payment.
Concreting
57 SWMS🧱Concreting SWMS
Formwork, reinforcement placement, concrete pour, finishing, and curing for slabs, footings, and walls.
🧱Bored Pier & Pile SWMS
Concreting of bored piers and piles in foundation work. Includes shaft cleanout, cage placement, tremie or pump-line concrete pour, level mo…
🧱Concrete Curing SWMS
Curing of fresh concrete via water cure, membrane cure, or plastic sheet cure. Includes timing of cure start, moisture application, sheet pl…
🧱Concrete Cutting & Sawing SWMS
Concrete cutting and sawing involves using diamond blades on hand-held saws, floor saws and wall saws to cut concrete, masonry and stone. Th…
🧱Concrete Finishing — Float & Trowel SWMS
Concrete finishing involves floating, trowelling, edging, brooming and curing of freshly placed concrete to achieve the specified surface fi…
🧱Concrete Grinding & Polishing SWMS
Concrete grinding and polishing involves using diamond-cup grinders, planetary grinders and polishing machines to smooth, level or finish co…
🏗️Concrete Pool Construction (Concreter Side) SWMS
SWMS template for concrete pool construction (concreter side). Covers Pool excavation, reo cage, shotcrete shell. 8-state AU coverage, CIH-r…
🧱Concrete Pouring — Slab on Ground & Suspended SWMS
Concrete pouring covers placement of ready-mix concrete for slabs on ground, suspended slabs, footings, columns and walls. The work involves…
🧱Concrete Pumping Operations SWMS
Concrete pumping involves using boom pumps or line pumps to place concrete at locations not accessible by direct truck discharge. Boom pump …
🏗️Concrete Repair SWMS
Safe Work Method Statement covering the key hazards and control measures for concrete repair.
🧱Concrete Saw Use — Hand-Held & Floor Saw SWMS
Concrete saw use covers the operation of hand-held demolition saws (cut-off saws), walk-behind floor saws and wall saws for cutting concrete…
📡Concrete Scanning SWMS
Safe Work Method Statement covering the key hazards and control measures for concrete scanning.
🧱Slab Pour SWMS
Concrete slab pour for residential / commercial floor slabs. Includes formwork prep, reinforcement check, screed-rail setup, pour sequencing…
🧱Concrete Works + Excavation SWMS
Combined concreting and excavation work covers footing trenches, slab edge excavation, wet concrete handling for in-ground pours, soil stock…
🧱Decorative Finishes SWMS
Decorative concrete finishing — broom finish, trowel finish, salt finish, integral colour, micro-toppings. Includes finish-specific tool use…
💉Epoxy Injection SWMS
Safe Work Method Statement covering the key hazards and control measures for epoxy injection.
🧱Exposed Aggregate SWMS
Install of exposed aggregate concrete — decorative or external paving finish. Includes pour with selected aggregate top layer, surface set r…
🧱Formwork Stripping SWMS
Formwork stripping (striking) involves removing formwork and temporary propping after concrete has achieved adequate strength. Premature str…
🔩FRP Strengthening SWMS
Safe Work Method Statement covering the key hazards and control measures for frp strengthening.
🏗️Kerb Machine Extrusion SWMS
SWMS template for kerb machine extrusion. Covers Slip-form kerb extruder, live traffic interface.. 8-state AU coverage, CIH-reviewed editabl…
🏗️Polished Concrete Floor Finishing SWMS
SWMS template for polished concrete floor finishing. Covers Diamond grinding, densifier, polish. 8-state AU coverage, CIH-reviewed editable …
🧱Post-Tensioning Operations SWMS
Post-tensioning involves stressing steel tendons within concrete slabs, beams and walls after the concrete has reached specified strength. T…
🏗️Pre-cast Tilt-up Panels SWMS
Pre-cast tilt-up concrete panel erection covers crane lift planning, lifting insert engineering, propping schedule per AS 3850, lateral brac…
🧱Precast Erection SWMS
Erection of precast concrete elements — beams, columns, panels, hollowcore planks. Includes site delivery and offload, rigging and lifting, …
🧱Rebar Installation & Tying SWMS
Rebar (reinforcing steel) installation involves cutting, bending, placing and tying steel reinforcement bars in formwork prior to concrete p…
🏗️Shotcrete / Sprayed Concrete SWMS
SWMS template for shotcrete / sprayed concrete. Covers Wet/dry mix shotcrete for tunnel, retaining wall, pool shells.. 8-state AU coverage, …
🏗️Spray-On Concrete Driveway Coating SWMS
SWMS template for spray-on concrete driveway coating. Covers Driveway resurfacing, sealer + colour.. 8-state AU coverage, CIH-reviewed edita…
🧱Stamped Concrete SWMS
Install of stamped or decorative concrete — driveways, patios, pool surrounds. Includes colour broadcast, release agent application, stamp p…
🧱Tilt-Up Panel Erection SWMS
Tilt-up panel erection involves casting concrete wall panels on the ground slab and then lifting (tilting) them into position using cranes. …
Formwork
5 SWMS🏗️Formwork SWMS
Formwork erection, stripping, and reshoring for concrete structures — wall panels, columns, beams, and suspended slabs. Propping loads, deck…
🏗️Formwork Erection (Traditional) SWMS
SWMS template for formwork erection (traditional). Covers Slab + wall + column form erection, bracing, deck. 8-state AU coverage, CIH-review…
🏗️Jump-Form / Slip-Form Concrete Construction SWMS
SWMS template for jump-form / slip-form concrete construction. Covers High-rise core construction methodology, climbing systems.. 8-state AU…
Applicable standards & regulations
Frequently asked questions
Is concreting classified as high risk construction work under WHS Regulation 2025?
Concreting itself is not automatically HRCW, but most concreting activities trigger HRCW classifications under WHS Regulation 2025 clause 291. Formwork above 2 metres, tilt-up and precast panel erection, post-tensioning involving structural alterations, concrete cutting in contaminated atmospheres, and work near energised services all qualify. A documented SWMS must be prepared before work starts and kept available for inspection. The Model Code of Practice: Construction Work confirms each HRCW trigger requires its own controls within the SWMS.
Do I need a separate SWMS for concrete pumping if I already have a pouring SWMS?
Yes. Concrete pumping introduces distinct hazards — line blockages, hose whip, boom contact with overhead powerlines, and high-pressure ejection — not covered in a general pour SWMS. WHS Regulation 2025 requires SWMS controls to match the actual activity. AS 2550.15 governs concrete placing equipment, and pump operators must follow boom exclusion zones. A dedicated Concrete Pumping SWMS documents these controls including the 6.4 m minimum clearance from energised lines under the Code of Practice: Excavation Work and electrical safety regulations.
What standards apply to tilt-up and precast panel erection SWMS?
Tilt-up and precast erection is explicitly listed as HRCW under WHS Regulation 2025 clause 291(l). AS 3850 Prefabricated Concrete Elements governs design, lifting inserts, bracing capacity and erection sequencing. The SWMS must reference panel weights, certified lifting points, brace angles, exclusion zones, weather limits and crane capacity. The Code of Practice: Tilt-up and Precast Concrete Construction (where adopted in your jurisdiction) details specific controls. Engineering certification of bracing and lifting inserts must be available before erection commences.
Are state-specific concreting SWMS required, or is one national template sufficient?
Australia operates under harmonised WHS laws across most jurisdictions, so a single SWMS template aligned with the model WHS Regulation 2025 is generally compliant. However, Victoria and Western Australia have variations, and some Codes of Practice are adopted differently. Our templates are written to harmonised standards and reference the model Code of Practice: Construction Work, with notes for jurisdictional differences. The PCBU must still review the SWMS for the specific site, workforce and plant before sign-on.
What is the difference between a SWMS and a JSA for concreting work?
A SWMS is a legally mandated document under WHS Regulation 2025 Part 6.3 for high risk construction work, with prescribed content: hazards, controls, responsibilities and review triggers. A JSA (Job Safety Analysis) is a broader risk assessment tool not legislatively required and without prescribed format. For concreting activities classified as HRCW — formwork at height, tilt-up, post-tensioning, cutting in contaminated atmospheres — a SWMS is mandatory. A JSA may supplement it for non-HRCW tasks like finishing or curing.
Concreting & Formwork SWMS
Editable DOCX templates, 8 state variants per product, CIH-reviewed.
Browse all SWMS