OH Consultant
🧱

Bored Pier & Pile Concreting SWMS

Concreting of bored piers and piles in foundation work. Includes shaft cleanout, cage placement, tremie or pump-line concrete pour, level monitoring, top-up after concrete settlement.

βš–οΈWHS Regulation 2025 & Codes of Practice β€” legally binding from 1 July 2026 (s26A)
πŸ‘·Reviewed by certified occupational health and safety professionals
πŸ—ΊοΈState-specific variants for all 8 Australian jurisdictions
$199 AUDβœ“ Instant Download Available

SWMS variants reference your state’s WHS legislation. Instant download after payment.

Bored pier and pile concreting involves placing reinforcement cages and discharging fluid concrete into augered shafts that frequently exceed two metres in depth and form part of a building's foundation system. The task combines confined shaft hazards, powered mobile plant interaction (concrete trucks, line pumps, piling rigs, telehandlers, service cranes), manual handling of heavy tremie sections and chute components, and time-critical pour management before initial set. Under WHS Regulation 2025 section 291, work in or near a shaft deeper than 1.5 m is classified as High Risk Construction Work, mandating a Safe Work Method Statement be prepared, signed by all workers, and kept available on site until the task is complete. The PCBU must consult workers during development, communicate the SWMS at pre-start, and review it whenever site conditions, plant or sequence change. This SWMS addresses shaft cleanout, cage handling, tremie or pump-line pour, level monitoring and post-settlement top-up in a single integrated document.

Hazards identified

7 hazards covered, sorted by priority.

Engulfment or fall into open pier shaft prior to concrete placementHIGH

Fatal crush asphyxiation, traumatic injury, breach of WHS Reg 2025 s305 excavation duties and corporate manslaughter exposure

Collapse of unlined or partially cased shaft wall during cleanout or cage placementHIGH

Worker buried below ground, fatal asphyxiation, prosecution under s19 primary duty of care

Struck-by suspended reinforcement cage during crane lift into shaftHIGH

Crushing injuries, fractures, fatality from cage swing or sling failure, notifiable incident under Part 3

Concrete truck or line pump reversing into pedestrian workers around shaft collarHIGH

Run-over fatality or serious lower-limb crush injury, breach of mobile plant separation duties

Pump-line blockage, whip and burst at delivery hose or reducerHIGH

High-velocity concrete impact causing eye loss, facial fractures, severe lacerations and chemical burns to bystanders

Manual handling of tremie pipe sections, hopper, and chute extensionsMEDIUM

Acute back, shoulder and crush injuries; cumulative musculoskeletal disorders triggering workers compensation claims

Wet concrete skin contact and alkali burns during top-up and finishingMEDIUM

Chemical burns, allergic contact dermatitis, chromate sensitisation requiring long-term medical management

Control measures

Hierarchy-of-controls order: elimination β†’ substitution β†’ isolation β†’ engineering β†’ administrative β†’ PPE.

  1. 1Elimination β€” Where pier design allows, eliminate manual shaft entry by specifying full-depth permanent casing and surface-discharge tremie methods at the design review stage.
  2. 2Elimination β€” Sequence works so reinforcement cage fabrication occurs offsite at ground-mounted jigs, removing the need for above-shaft welding or tying over an open hole.
  3. 3Substitution β€” Substitute heavy steel tremie sections with lightweight aluminium or quick-coupling polymer-lined segments to reduce manual handling forces below 20 kg per lift.
  4. 4Substitution β€” Replace open chute discharge with closed boom-pump placement to remove concrete free-fall splash exposure to workers at the shaft collar.
  5. 5Engineering β€” Install proprietary edge-protection collars, mesh covers and 1.0 m hard barricades at every shaft immediately after auger withdrawal per AS 2865 confined space and AS/NZS 4994 fall protection principles.
  6. 6Engineering β€” Use radio-equipped concrete pump operators, line-pressure relief valves and certified clamps on every coupling, with hose whip restraints fitted at all reducers.
  7. 7Administrative β€” Conduct pre-start brief using this SWMS, confirm exclusion zones, nominate a single dogger/spotter for cage lifts, and verify high-risk work licences for crane and pump operators.
  8. 8Administrative β€” Implement a permit-to-pour system requiring shaft depth, cleanout, cage tolerance and groundwater checks to be signed off before any concrete leaves the agitator.
  9. 9Administrative β€” Rotate workers off finishing and top-up tasks every 60 minutes to limit cumulative wet concrete contact and manual handling exposure during continuous pours.
  10. 10PPE β€” Issue alkali-resistant gauntlets, full-length waterproof trousers, sealed safety boots, sealed safety glasses or face shield for pump operators, hi-vis, and hard hat with chinstrap near suspended loads.

Applicable Codes of Practice

AS 2159:2009 Piling β€” Design and Installation

Defines shaft stability, concrete placement rate, cage tolerance and tremie immersion depth requirements that directly govern safe pour sequencing.

Safe Work Australia Code of Practice β€” Excavation Work (2018, adopted under WHS Regulation 2025)βš– Legally binding Β· 1 Jul 2026

Triggers shaft classification, ground-support assessment, edge protection and emergency rescue planning for pier shafts exceeding 1.5 m depth.

Safe Work Australia Code of Practice β€” Managing the Risks of Plant in the Workplaceβš– Legally binding Β· 1 Jul 2026

Governs exclusion zones, spotter protocols and traffic management for concrete agitators, line pumps and piling rigs around active shafts.

AS 3610.1:2018 Formwork for Concrete and AS 1379:2007 Specification and Supply of Concrete

Sets slump, retardation and supply tolerances ensuring concrete remains workable through tremie placement, reducing blockage and burst-line risk.

High-Risk Construction Work triggered

s291(g)
Is carried out in or near a shaft or trench deeper than 1.5 metres, or a tunnel

Bored pier shafts routinely extend 3 to 25 metres below ground, placing all cleanout, cage placement and tremie work within section 291 category.

s291(o)
Is carried out in an area at a workplace in which there is any movement of powered mobile plant

Workers manage tremie, hose and finishing tasks within the operating radius of multiple plant items moving simultaneously during continuous concrete supply.

Legal consequence

PCBU must prepare, consult workers on, and retain this SWMS for two years post-incident or until task completion; penalties for non-compliance are substantial and indexed, with the current maximum following the prevailing WHS schedule.

Who this is for

  • β†’Piling subcontractors on commercial and infrastructure projects
  • β†’Principal contractors managing deep foundation packages
  • β†’Concrete pump operators servicing bored pier works
  • β†’Site supervisors and engineers overseeing geotechnical construction

What you receive

  • βœ“Editable DOCX template β€” Microsoft Word compatible
  • βœ“State-specific WHS legislation schedule (NSW/VIC/QLD/SA/WA/TAS/NT/ACT)
  • βœ“Hazard register with risk ratings + hierarchy-of-control mapping
  • βœ“Worker sign-on register, pre-start checklist, and incident escalation flow

Worked example

On a mid-rise residential basement project, a piling crew is scheduled to pour twelve 900 mm diameter bored piers averaging 14 metres deep across a single day shift. At the 6:30 am pre-start, the leading hand opens this SWMS on the site tablet and walks the four-person crew, the pump operator, the dogger and the agitator driver through each hazard line by line. When reviewing the shaft engulfment hazard, the dogger flags that the steel collars from yesterday are still stacked at the laydown β€” the supervisor pauses the brief, sends two workers to refit collars and mesh covers to all uncast shafts, and updates the daily addendum. The crew confirms the exclusion zone radius for the line pump, agrees on a single radio channel between dogger and pump operator, and each worker signs the SWMS register. Mid-pour on pier seven, the pump line develops a partial blockage. Because the SWMS pre-identified whip risk, the operator already has the whip restraint fitted and clears the line from outside the exclusion zone using the pre-agreed pressure-relief procedure. The supervisor records the deviation, briefs the change at smoko, and the crew re-signs the amended SWMS before the afternoon piers are poured, demonstrating live document use rather than shelf compliance.

Related legislation

  • WHS Act 2011 (model)
  • WHS Regulation 2025
  • AS 2550 β€” Cranes, hoists and winches; AS 1418 series

Frequently asked questions

Is bored pier concreting high risk construction work?

Yes, on two counts. Pier shafts routinely run from three to twenty-five metres, so cleanout, cage placement and tremie work are all carried out in or near a shaft deeper than 1.5 metres β€” section 291(g) of the WHS Regulation. Separately, agitator trucks, line pumps, piling rigs and service cranes operate around the shaft collar throughout the pour, which engages section 291(o), work in an area with movement of powered mobile plant. Section 299 then requires the SWMS be prepared before work starts, developed in consultation with the workers doing it, signed on, and reviewed whenever plant, sequence or ground conditions change.

What licences do the crane and pump crew need?

High risk work licences are verified at the pre-start rather than assumed. A dogging or rigging licence covers the person directing the reinforcement cage lift into the shaft, and the crane operator holds the class matching the machine. Concrete placing boom operation carries its own high risk work licence class. Beyond the licence itself, the document requires one nominated dogger or spotter per lift β€” not several people calling directions β€” and a single agreed radio channel between that person and the pump operator, because a suspended cage over an open shaft with two voices on the channel is how workers get struck.

Does this cover tremie pours and pump-line placement, or only chute discharge?

All three, and the document actively steers away from open chute discharge. Closed boom-pump placement is preferred because it removes the splash exposure at the shaft collar, and tremie placement is covered including immersion depth and cage tolerance drawn from AS 2159. Concrete supply is treated as a safety input rather than only a quality one: slump and retardation specified under AS 1379 keep the mix workable through the tremie or line, which is what prevents the blockages that lead to line whip and burst couplings. Lightweight quick-coupling tremie segments are specified so individual lifts stay manageable.

How is an open shaft protected, and does anyone have to climb into it?

The design intent is that nobody enters. The elimination control specifies full-depth permanent casing and surface-discharge tremie methods at design review, so cleanout and placement happen from the collar. Cage fabrication moves to ground-mounted jigs, so no one is tying or welding over an open hole. Every shaft gets a proprietary edge-protection collar, mesh cover and hard barricading immediately after the auger withdraws, not at the end of the shift. If entry ever becomes unavoidable, that is confined space work with its own permit, atmospheric testing, standby person and rescue plan, and it sits outside the scope of this document.

What do I receive, and how is it meant to be used during a pour?

You receive an editable Microsoft Word document, bought once, containing the hazard register with risk ratings, the full control set, the permit-to-pour checks covering shaft depth, cleanout, cage tolerance and groundwater, a worker sign-on register and the legislation schedule for your jurisdiction. It is written to be briefed line by line at the tailgate and amended during the shift. If collars are missing from uncast shafts, or a line blockage changes the clearing procedure, you stop, record the change as a dated addendum and have the crew re-sign before the next pier is poured.

What's in this SWMS

Document details

Regulation
WHS Regulation 2025, Schedule 1 β€” High Risk Construction Work
HRCW Category
Cat 2 (work in shaft), powered mobile plant, manual handling
Hazards Identified
7 hazards with controls
Format
Editable DOCX (Microsoft Word)
Author
Certified Industrial Hygienist (CIH)
Delivery
Instant download after payment
CIH-reviewed SWMS Β· from $99 Β· instant download

Related SWMS templates

πŸ“‹Concreting JSA SWMS

This template breaks a complete concreting task into its real work sequence β€” pre-pour planning, formwork and …

$99 AUDBuy β†’

🧱Concrete Curing SWMS

Curing of fresh concrete via water cure, membrane cure, or plastic sheet cure. Includes timing of cure start, …

$99 AUDBuy β†’

🧱Exposed Aggregate SWMS

Install of exposed aggregate concrete β€” decorative or external paving finish. Includes pour with selected aggr…

$149 AUDBuy β†’

🧱Concreting SWMS

Formwork, reinforcement placement, concrete pour, finishing, and curing for slabs, footings, and walls.

$199 AUDBuy β†’

🚜Civil Drilling & Piling SWMS

Civil drilling and piling covers CFA pile installation, bored pier construction, screw pile install, drilling …

$149 AUDBuy β†’

🧱Concrete Pumping Operations SWMS

Concrete pumping involves using boom pumps or line pumps to place concrete at locations not accessible by dire…

$149 AUDBuy β†’