Free Job Hazard Analysis (JHA) Template (Australia)
A step-by-step task breakdown with the hazards, risk rating and controls for each step, on a single sheet the crew can sign.
What this template is for, and when you need it
A job hazard analysis (JHA), also called a job safety analysis (JSA) or JSEA, breaks a task into its steps, lists the hazards at each step, rates the risk and records the controls that will be used. It is written for one task, usually by the supervisor with the people doing the work, and it is short enough to be read at the pre-start.
No Australian WHS law requires a document called a JHA. The duty it supports is the general one: a person conducting a business or undertaking must identify hazards, assess and control risks and review the controls, and must consult the workers affected. Safe Work Australia’s code of practice How to Manage Work Health and Safety Risks describes that process; a JHA is the common way of recording it for a single task. Many principal contractors, mines and plants ask contractors for a JHA for every non-routine job.
A JHA is not a SWMS. For high risk construction work (the 18 categories listed in the WHS Regulations of each harmonised state and territory, with Victoria’s own list under the OHS Regulations 2017) a SWMS is required before the work starts, and a JHA cannot stand in for it. Use this JHA for tasks outside those categories, for maintenance and plant work, and as a pre-start tool that feeds the SWMS on construction sites.
THE PAID DOCUMENT THAT GOES WITH IT
JSA templates by taskPre-written job safety analyses with the steps, hazards and controls already filled in for common tasks, in editable Word.
GO DEEPER (FREE GUIDE)
What is a JSA?The template, section by section
This is the full content of the Word file. Text in square brackets is replaced with your own; blue text inside the form cells is a hint about what goes there.
FREE TEMPLATE
Job Hazard Analysis (JHA)
A step-by-step task breakdown with the hazards, risk rating and controls for each step, on a single sheet the crew can sign.
Part 1 — Task details
| Task / job | |
|---|---|
| Site / location | |
| Date | |
| Prepared by | Name and role |
| Workers consulted | |
| Supervisor | |
| Permits, licences and SWMS that apply | e.g. hot work permit, high risk work licence class, SWMS number |
| Plant, tools and chemicals used | List safety data sheets held |
| PPE required for the whole task |
Part 2 — Risk matrix
| Likelihood ↓ / Consequence → | 1 Insignificant | 2 Minor | 3 Moderate | 4 Major | 5 Catastrophic |
|---|---|---|---|---|---|
| 5 Almost certain | Medium (5) | High (10) | High (15) | Extreme (20) | Extreme (25) |
| 4 Likely | Medium (4) | Medium (8) | High (12) | High (16) | Extreme (20) |
| 3 Possible | Low (3) | Medium (6) | Medium (9) | High (12) | High (15) |
| 2 Unlikely | Low (2) | Low (4) | Medium (6) | Medium (8) | High (10) |
| 1 Rare | Low (1) | Low (2) | Low (3) | Medium (4) | Medium (5) |
- Rate each step twice: before controls (inherent) and after the controls listed (residual).
- Extreme: do not start; eliminate or redesign the task. High: start only with the supervisor’s written approval and the controls in place. Medium: proceed with the controls listed. Low: manage by routine procedures.
- Choose controls from the top of the hierarchy down: Eliminate · Substitute · Isolate · Engineering · Administrative · PPE. PPE alone is not an adequate control for a serious risk.
Part 3 — Task steps, hazards and controls
| Step | Task step (in order) | Hazards (what could cause harm) | Inherent risk | Control measures | Residual risk | Who |
|---|---|---|---|---|---|---|
| 1 | Set up and isolate the work area | Pedestrians and mobile plant entering; trip hazards from leads and hoses | High (12) | Barricade and sign the area; agree an exclusion zone with the site supervisor; route leads overhead or cover them | Low (3) | Supervisor |
| 2 | ||||||
| 3 | ||||||
| 4 | ||||||
| 5 | ||||||
| 6 | ||||||
| 7 | ||||||
| 8 |
Row 1 is an example
Replace it with the first step of your own task. Add rows as needed; a task with more than about twelve steps is usually two tasks.
Part 4 — Emergency and review
| Emergency arrangements for this task | First aid, rescue, nearest assembly point, who to call |
|---|---|
| Review this JHA when | The task, the site, the plant or the crew changes; after an incident or near miss; before the task is repeated at a new location |
Part 5 — Sign-on
I took part in preparing or was briefed on this JHA, I understand the hazards and controls, and I will stop work and tell the supervisor if conditions change.
| Name | Company | Signature | Date |
|---|---|---|---|
The Word file has 8 blank rows.
| Role | Name | Signature | Date / time |
|---|---|---|---|
| Supervisor (approved to start) |
OH Consultant · swms.ohconsultant.com.au/swms/free/job-hazard-analysis · Free template, not legal advice.
Other free templates
A general risk assessment form with a 5×5 risk matrix, likelihood and consequence definitions, the hierarchy of control and an action plan.
A one-page record of the daily safety talk: topic, key points, questions raised, actions and the attendance sign-on.
The daily pre-start on one page: site conditions, permits, plant, people and the SWMS check, with the crew sign-on.
You are welcome to link to this page or to the download, and to use and adapt the template within your business; please keep the attribution line in the footer. The template is general information, not legal advice: work health and safety laws differ between states and territories, so check the requirements that apply where the work is done.