When a Site Safety Management Plan Is Required
Under the WHS Regulations a construction project is construction work where the cost of the work is $250,000 or more. Every construction project must have a principal contractor, and the principal contractor must prepare a written WHS management plan before work on the project commences (section 309 of the NSW WHS Regulation, regulation 309 in the other WHS jurisdictions). The person who commissions the work is the principal contractor unless they appoint someone else and give that person management or control of the site, which is what a head contract with a builder normally does.
Victoria works under its own law. The Occupational Health and Safety Regulations 2017 require the principal contractor to prepare a health and safety coordination plan for a construction project costing $350,000 or more. The contents are close to the WHS management plan, and a plan written to the outline below satisfies both once the Victorian terms and references are used.
Below the threshold there is no duty to prepare the plan, but the duties it organises still apply: the builder must still manage risks, consult, plan for emergencies and collect a SWMS for any high risk construction work. Many clients, councils and head contractors ask for a site safety plan on smaller jobs for exactly that reason.
The Five Items the Regulations Require
The plan must include:
-
The names, positions and health and safety responsibilities of everyone at the workplace whose position or role involves specific health and safety responsibilities for the project. This means named people, such as the site supervisor, the first aiders and the person who issues permits, with what each is responsible for.
-
The arrangements for consultation, cooperation and coordination between the businesses working on the project. In practice: pre-start meetings, toolbox talks, the subcontractor coordination meeting and how issues are raised and closed.
-
The arrangements for managing any work health and safety incidents that occur: who is told, who preserves the scene, who notifies the regulator of a notifiable incident, and how the investigation is recorded.
-
Any site-specific health and safety rules, and the arrangements for making sure everyone at the workplace is told about them. This is the site induction and the rules it teaches.
-
The arrangements for collecting, assessing, monitoring and reviewing safe work method statements. The principal contractor must obtain a SWMS before high risk construction work starts and must see that the work follows it.
A plan that covers these five items meets the regulation. A plan that only covers these five rarely satisfies a client or an auditor, which is where the site-specific sections come in.
What Makes the Plan Site-Specific
The commonest reason a plan is rejected is that it could describe any site. A site safety management plan earns the name when it records the things that are true of this job and no other:
- The site and its surroundings. Address, boundaries, neighbouring properties, schools, public footpaths, overhead power lines and underground services, with a site layout plan showing access points, amenities, first aid, the emergency assembly area, material storage and plant routes.
- The hazards of this project. A project hazard register built from the actual scope: demolition, excavation depth, work at height, cranes, asbestos found in the survey, silica-generating tasks, traffic.
- The high risk construction work on the programme, listed against the subcontractor responsible and the SWMS received.
- Traffic and pedestrian management for deliveries, plant movements and the public interface.
- Emergency arrangements for this location: the nearest hospital, access for emergency vehicles, rescue arrangements for work at height or confined spaces, and the evacuation procedure.
- Permits used on the site, such as hot work, excavation, confined space and work at height, and who is authorised to issue them.
- Amenities, first aid and site security, including after-hours arrangements and public protection.
Who Writes It and Who Must See It
The principal contractor is responsible for the plan. It may be drafted by a safety adviser or a consultant, but the principal contractor remains accountable for its content and for following it.
Before a person starts work on the project, the principal contractor must make sure, so far as is reasonably practicable, that the person is made aware of the content of the plan that relates to the work they will do and of their right to inspect it. That is normally done through the site induction. The plan must be reviewed and revised as necessary so that it stays up to date, and everyone affected must be told of the revision. A copy must be kept until the project is completed, and for at least two years after a notifiable incident occurs.