Truck-Mounted Crane Operation SWMS
Operation of truck-mounted articulating crane (Hiab / Palfinger) for material delivery and lifting. HRWL CN or C0 licensing, outrigger deployment on suitable ground, swing radius exclusion, lift planning.
SWMS variants reference your stateβs WHS legislation. Instant download after payment.
Truck-mounted articulating cranes (commonly Hiab, Palfinger or Effer units) are used across construction, landscaping, civil and materials supply sectors to load, transport and place palletised goods, precast elements, steel, plant and bulk bagged product. Operation of this plant constitutes High Risk Construction Work under section 291 of the WHS Regulation 2025 because it involves powered mobile plant, lifting operations over or near workers, and frequently occurs adjacent to public roads or live traffic. Operators must hold the relevant HRWL (CN slewing or C0 non-slewing) class, and the PCBU must prepare, consult on and implement a Safe Work Method Statement before work commences. The SWMS must address ground-bearing capacity for outrigger deployment, exclusion zones within the swing radius, load chart compliance, rigging integrity and proximity to overhead electrical assets. This document provides a compliant, auditable SWMS aligned with WHS Reg 2025 s299βs306 duties.
Hazards identified
7 hazards covered, sorted by priority.
Crane overturn crushing operator, bystanders or property; fatal traumatic injury and total plant loss
Electrocution of operator and dogger via boom touch potential; arc flash burns and cardiac arrest
Crush fatality of workers below; structural damage; prosecution under WHS Reg 2025 s213βs216
Structural failure of boom or chassis tip-over; operator ejection and catastrophic plant loss
Crush injury between counterweight and fixed structure; impact fatality from swinging load
Load loss onto public roadway; third-party fatality; Chain of Responsibility prosecution under HVNL
Sudden load drop; high-pressure fluid injection injury to operator; struck-by injury to riggers below
Control measures
Hierarchy-of-controls order: elimination β substitution β isolation β engineering β administrative β PPE.
- 1Elimination β Where practicable, use forklift or telehandler delivery direct to ground level to remove the need for crane lifting over personnel entirely.
- 2Elimination β Schedule lifts outside hours when other trades are on site, eliminating concurrent activity exposure within the crane swing radius and drop zone.
- 3Substitution β Substitute heavy single lifts with smaller pre-split loads to remain within 75% of rated capacity on the manufacturer's load chart at working radius.
- 4Engineering β Deploy outriggers fully onto engineered timber or composite pads sized to keep ground bearing pressure below tested soil capacity (refer AS 2550.1).
- 5Engineering β Fit and verify operation of load moment indicator (LMI), anti-two-block, and boom angle limit devices before each shift per AS 1418.11.
- 6Administrative β Complete documented lift study for loads exceeding 80% capacity, including exclusion zone plan, dogger position and communication protocol per AS 2550.1.
- 7Administrative β Verify operator holds current HRWL class CN or C0, dogger holds DG licence, and both are recorded on the SWMS sign-on register before commencement.
- 8Administrative β Maintain minimum approach distance from overhead powerlines per Code of Practice Working Near Overhead and Underground Electric Lines; use spotter where within 6.4 m.
- 9PPE β Wear AS/NZS 1801 hard hat, AS/NZS 1337.1 impact eyewear, AS/NZS 2210.3 steel-cap boots and AS/NZS 4602.1 Class D/N hi-vis during all lifting operations.
- 10PPE β Riggers and doggers to wear AS/NZS 2161.2 cut-resistant gloves when handling wire rope slings, chains and shackles to prevent laceration and pinch injury.
Applicable Codes of Practice
Specifies design, stability, load chart, and safety device requirements for articulating truck-mounted cranes; defines pre-operational inspection duties.
Establishes lift planning, outrigger setup, ground assessment and exclusion zone obligations referenced directly in WHS Reg 2025 s213 plant duties.
Codifies PCBU duty to assess, control and review powered mobile plant risks; mandates operator competency verification and isolation procedures.
Sets minimum approach distances, spotter requirements and permit conditions when operating crane booms in proximity to live overhead conductors.
High-Risk Construction Work triggered
Crane deployment zone overlaps with delivery vehicles, site traffic and pedestrian routes, creating concurrent powered mobile plant interaction requiring traffic management.
Boom extension and slew commonly occurs within proximity zones of overhead distribution lines on urban and roadside material delivery tasks.
PCBU must prepare SWMS, consult workers, and retain records for the project duration plus 2 years post-incident; penalties are substantial and indexed, current maximum follows the prevailing WHS schedule.
Who this is for
- βTruck-mounted crane operators holding HRWL CN/C0
- βTransport and logistics PCBUs delivering building materials
- βCivil contractors performing precast and steel placement
- βSite supervisors coordinating lifts on construction projects
What you receive
- βEditable DOCX template β Microsoft Word compatible
- βState-specific WHS legislation schedule (NSW/VIC/QLD/SA/WA/TAS/NT/ACT)
- βHazard register with risk ratings + hierarchy-of-control mapping
- βWorker sign-on register, pre-start checklist, and incident escalation flow
Worked example
At a pre-start brief on a suburban townhouse civil works project, the truck-mounted crane operator and dogger open this SWMS on a tablet at the tailgate. The operator walks through the seven hazards with the site supervisor, focusing first on outrigger stability β the delivery point is on recently backfilled service trench, so the team selects the engineered composite outrigger pads listed in the engineering controls and increases pad footprint to keep bearing pressure below the geotech-tested 150 kPa limit. They identify a 22 kV overhead line running parallel to the kerb and apply the 6.4 m exclusion zone control from the Code of Practice, nominating a dedicated spotter and revising the lift sequence so the boom never slews north of the cab. Both workers sign the SWMS register, confirming HRWL currency. Mid-task, a plumber arrives unannounced and walks toward the swing radius. The dogger halts the lift using the agreed radio call sign, the operator parks the load, and the SWMS exclusion zone control is re-briefed with the plumber before resumption. The amendment, including the additional spotter position, is recorded in the SWMS variation log and re-signed by all workers, satisfying WHS Reg 2025 s301 review obligations.
Related legislation
- WHS Act 2011 (model)
- WHS Regulation 2025
- AS 2550 β Cranes, hoists and winches; AS 1418 series
Frequently asked questions
Is truck-mounted crane work high risk construction work?
Yes. The crane is powered mobile plant and doggers, riggers and ground crew stand within metres of a slewing boom and counterweight on every lift cycle, which engages WHS Regulation section 291(o). Boom extension and slew near overhead distribution lines on urban and roadside deliveries engages section 291(k), and unloading beside a live carriageway engages section 291(n). Section 299 requires the SWMS to be prepared in consultation with the workers doing the lift and complied with on site. Delivering to a residential driveway is no exception β most vehicle loading crane incidents happen on short, routine drops.
What licences do the operator and dogger need?
A high risk work licence in the class that matches the machine, plus a dogging licence for whoever directs the lift. A vehicle loading crane rated at 10 metre tonnes or more requires the vehicle loading crane class; slewing and non-slewing mobile cranes have their own classes and rated capacity limits, so check the plate against the licence rather than assuming. The person slinging the load and directing the operator when the load is out of sight needs a dogging licence. Both are recorded on the SWMS sign-on register before the first lift. Buying this document does not confer any licence.
How does it deal with outrigger ground bearing and load chart limits?
Outriggers are deployed fully onto engineered timber or composite pads sized so ground bearing pressure stays below the tested capacity of the surface, in line with AS 2550.1 β punch-through on soft or recently backfilled ground is the usual mechanism behind a vehicle loading crane rollover. In the worked example the drop point sits over a backfilled service trench, so the pad footprint is increased to hold pressure under the geotechnical limit. On capacity, heavy single lifts are pre-split to stay within 75 per cent of rated capacity at working radius, and anything above 80 per cent requires a documented lift study.
What are the rules for overhead powerlines and the swing radius?
Keep the boom outside the minimum approach distance set by the Code of Practice for working near overhead and underground electric lines, which varies with voltage and jurisdiction β in the worked example a 22 kV line running parallel to the kerb draws a 6.4 m exclusion, a dedicated spotter, and a revised lift sequence so the boom never slews toward the conductors. On the ground, the swing radius is a no-go zone with an agreed radio call sign that any worker can use to halt a lift. When an unannounced trade walks toward it, the load is parked, the exclusion is re-briefed and the variation is logged.
What safety devices are checked, and what do I actually receive?
The load moment indicator, anti-two-block and boom angle limit devices are verified as functioning before each shift under AS 1418.11, alongside rigging and hook latch inspection, because a failed or unrated sling drops the load onto whoever is below. You receive an editable Word document, purchased once, holding the hazard register with risk ratings, hierarchy-of-control mapping, a state-specific legislation schedule for NSW, VIC, QLD, SA, WA, TAS, NT and the ACT, a sign-on register, pre-start checklist and incident escalation flow. Field changes such as adding a spotter position go in the variation log and are re-signed before work resumes.
Document details
Related SWMS templates
ποΈHIAB Truck Loader Crane SWMS
HIAB knuckle-boom and truck-mounted loader crane operations β crane set-up, outrigger deployment, lift planninβ¦
ποΈMobile Crane Lifts SWMS
Franna, city crane, slewing mobile crane and hydraulic truck-crane operations β lift-plan development, outriggβ¦
πBoom Lift SWMS
Articulating and telescopic boom lift operations including ground assessment, outrigger setup, and operation.
πCrane & Lifting JSA SWMS
This template covers mobile crane lifting operations β slewing and non-slewing mobile cranes and vehicle loadiβ¦
ποΈVehicle-Mounted Loading Crane (VMLC) Operation SWMS
SWMS template for vehicle-mounted loading crane (vmlc) operation. Covers Truck-mounted crane >10t/m operation,β¦
ποΈTower Crane Operations SWMS
Tower crane erection oversight, daily pre-start inspection, lifting operations, blind-lift management, slew anβ¦