Below-Ground Tanking & Basement Waterproofing SWMS
Below-ground tanking and basement waterproofing β excavated basement walls, raft slabs, and lift pits. Cementitious slurry, positive-side sheet membrane, drainage cell, and protection board.
SWMS variants reference your stateβs WHS legislation. Instant download after payment.
Below-ground tanking and basement waterproofing is a high-risk construction activity involving the application of cementitious slurries, positive-side sheet membranes, drainage cell, and protection board to excavated basement walls, raft slabs, and lift pits. The work occurs in partially enclosed or fully confined spaces adjacent to unsupported or shored excavations, often in the presence of groundwater ingress, solvent-based primers, and gas-fired torches or hot-air welders. Under WHS Regulation 2025 Part 6.3, this activity is classified High Risk Construction Work because it is performed in or near a confined space, adjacent to excavation deeper than 1.5 m, and frequently involves the use of flammable substances in enclosed atmospheres. A documented Safe Work Method Statement is mandatory before work commences, must be developed in consultation with workers, kept accessible at the workplace, and reviewed if controls are revised or an incident occurs. Failure to prepare and implement a compliant SWMS exposes the PCBU, principal contractor, and supervising officers to enforceable WHS duties and category 1β3 offences.
Hazards identified
7 hazards covered, sorted by priority.
Loss of consciousness, asphyxiation, chemical pneumonitis, and delayed central nervous system depression requiring hospitalisation
Crush asphyxia, multi-system trauma, fatality, and prosecution under WHS Reg 2025 Part 6.3 excavation duties
Flash fire, deflagration in confined basement, severe partial-thickness burns, and structural fire spread
Acute lumbar disc herniation, crush injuries to lower limbs, falls from ladder, and chronic musculoskeletal disorder claims
Falls greater than 2 m causing fractures, head injury, spinal cord damage, and notifiable incident reporting
Allergic contact dermatitis, chrome ulceration, occupational asthma, and long-term sensitisation requiring medical removal
Fractures, lacerations, secondary fall into pit penetrations, and lost-time injury exceeding statutory thresholds
Control measures
Hierarchy-of-controls order: elimination β substitution β isolation β engineering β administrative β PPE.
- 1Elimination β Specify pre-applied bonded membrane systems installed on blinding before reinforcement and pour, eliminating downstream confined-space and excavation-edge application entirely where design permits.
- 2Elimination β Sequence works so basement tanking is completed before lift-pit shaft formwork and surrounding services restrict access, removing the confined-space entry requirement for follow-on coats.
- 3Substitution β Substitute solvent-based bituminous primers with water-based or low-VOC acrylic primers compliant with AS/NZS 4858 to remove flammable-vapour and narcotic-vapour exposure inside the basement envelope.
- 4Substitution β Replace cementitious slurries containing hexavalent chromium with reduced-chromate cements complying with EN 196-10 limits to eliminate Cr(VI) dermal sensitisation risk.
- 5Engineering β Install forced mechanical ventilation delivering minimum 20 air changes per hour into lift pits and tanked rooms, with continuous LEL, O2 and VOC monitoring per Confined Space CoP 2021.
- 6Engineering β Install temporary edge protection to raft slab perimeter and pit penetrations, certified shoring or battered excavation faces to AS 5047, and powered conveyor or hoist for membrane roll handling.
- 7Administrative β Issue confined-space entry permit, stand-by attendant with two-way comms, atmospheric test log, and SWMS sign-on at every shift pre-start brief; suspend works if LEL exceeds 5%.
- 8Administrative β Implement hot-work exclusion zone of 6 m from any solvent application, lock out torches and welders during priming, and rotate manual-handling teams every 30 minutes.
- 9PPE β Supplied-air respirators or full-face A2P2 cartridge respirators for primer application, nitrile chemical gauntlets, Type 5/6 coveralls, chemical-splash goggles, and AS/NZS 2210 safety boots with puncture-resistant midsoles.
- 10PPE β AS/NZS 1891 compliant full-body harness with dual lanyard and rescue retrieval system anchored above any confined-space entry, plus FR coveralls during any residual hot-work activity.
Applicable Codes of Practice
Mandates entry permit, atmospheric testing, stand-by attendant, and rescue plan whenever lift pits or tanked rooms meet the confined-space definition.
Requires shoring, benching or battering and a competent-person inspection where membrane crews work adjacent to excavations deeper than 1.5 m.
Defines product compliance, primer compatibility, and substrate preparation referenced by the SWMS when selecting membrane and solvent systems.
Governs subsoil drainage cell discharge, agricultural drain connection, and overflow paths integrated with positive-side tanking systems.
High-Risk Construction Work triggered
Membrane application inside lift pits and sealed basement rooms with restricted egress and accumulating solvent vapours meets the confined-space definition under WHS Reg 2025.
Positive-side tanking is applied against retaining walls of basement excavations and lift-pit shafts that routinely exceed 1.5 m depth before backfill.
Solvent-based primers and adhesives generate flammable VOC atmospheres inside the enclosed basement envelope during application and cure-off periods.
PCBU must prepare the SWMS in consultation with workers, keep it accessible on site, review after any incident or control change, and retain it for at least two years; penalties for non-compliance are substantial and indexed annually under the prevailing WHS schedule.
Who this is for
- βSpecialist waterproofing subcontractors on basement projects
- βPrincipal contractors on multi-level residential basements
- βCivil contractors installing tanking to lift pits
- βRemedial waterproofers retrofitting below-ground structures
What you receive
- βEditable DOCX template β Microsoft Word compatible
- βState-specific WHS legislation schedule (NSW/VIC/QLD/SA/WA/TAS/NT/ACT)
- βHazard register with risk ratings + hierarchy-of-control mapping
- βWorker sign-on register, pre-start checklist, and incident escalation flow
Worked example
On a four-level residential basement project, the waterproofing leading hand arrives at 6:30 am to apply solvent-primed sheet membrane to the lift-pit shaft and southern retaining wall. At the pre-start brief held at the site shed, the crew of three opens this SWMS on a tablet and walks the controls register line by line against today's conditions. The leading hand confirms the lift pit is 2.4 m deep with a single 600 mm access opening, triggering the confined-space entry permit (control 7) and forced ventilation set-up (control 5). The atmospheric monitor is calibrated and lowered; baseline O2 reads 20.9% and LEL 0%. Because the original specification called for solvent primer, the team substitutes the water-based primer already approved in control 3, eliminating the hot-work exclusion zone conflict with grinders running on level above. Each worker signs on against the SWMS, acknowledging the rescue retrieval anchor point and stand-by attendant rotation. Two hours in, the monitor alarms at 6% LEL from a neighbouring trade's adhesive β work is immediately suspended per control 7, the pit is purged, and the SWMS is annotated with the deviation and corrective action before re-entry. The signed document and atmospheric log are filed with the principal contractor at shift end.
Related legislation
- WHS Act 2011 (model)
- WHS Regulation 2025
- AS 2865 β Confined spaces
Frequently asked questions
Is basement tanking high risk construction work?
Yes, and typically on three counts at once under WHS Regulation section 291: s291(f), work in or near a confined space, because lift pits and sealed tanked rooms qualify; s291(g)(i), work in or near a shaft or trench with an excavated depth greater than 1.5 m, because positive-side tanking is applied against basement retaining walls before backfill; and s291(l), work in an area that may have a contaminated or flammable atmosphere, because solvent primers build VOC inside an enclosed envelope. Section 299 requires the SWMS before work commences, prepared in consultation with the crew and kept accessible at the workplace.
Is a lift pit a confined space, and what does entry require?
Apply the definition test rather than a rule of thumb β restricted entry and egress, not intended for continuous occupancy, and capable of developing a hazardous atmosphere. The worked example's pit is 2.4 m deep with a single 600 mm opening, so it qualifies. Entry then needs a permit, calibrated atmospheric testing for oxygen, LEL and VOC, forced ventilation delivering at least 20 air changes per hour, a stand-by attendant on two-way comms, and a rescue retrieval system anchored above the opening. Membrane rolls of 40 to 60 kg go down by powered hoist or conveyor, never carried on the access ladder.
Can we avoid solvent-based primers and chromate cements?
Both substitutions are built into the control set. Solvent-based bituminous primers are replaced with water-based or low-VOC acrylic primers compliant with AS/NZS 4858, which removes the flammable and narcotic vapour load inside the basement and, in the worked example, also removes the clash with grinders running on the level above. Cementitious slurries containing hexavalent chromium are replaced with reduced-chromate cements meeting EN 196-10 limits, because Cr(VI) exposure during trowel application drives allergic contact dermatitis, chrome ulceration and long-term sensitisation.
What stops the excavation face collapsing onto the membrane crew?
Certified shoring or a battered face designed to AS 5047, with competent-person inspection wherever the crew works adjacent to an excavation deeper than 1.5 m. The stronger answer is higher up the hierarchy: specifying a pre-applied bonded membrane installed on blinding before reinforcement and pour removes the need to work against an open face at all, and sequencing tanking before lift-pit formwork and surrounding services keeps access open. Temporary edge protection to the raft slab perimeter and pit penetrations covers the residual fall exposure.
What triggers a stop-work, and what gets filed at shift end?
The atmospheric monitor is the hard trigger: work is suspended if LEL exceeds 5 per cent. In the worked example the monitor alarms at 6 per cent from a neighbouring trade's adhesive, the pit is purged, and the deviation and corrective action are annotated on the document before re-entry. Because you receive an editable Word document, that annotation is a real amendment. The signed document and the atmospheric test log are filed together with the principal contractor at shift end, the document is reviewed after any incident or control change, and it is retained for at least two years.
Document details
Related SWMS templates
π§Waterproofing SWMS
Waterproofing and membrane installation for wet areas, roofs, podiums, and below-ground structures β sheet memβ¦
π§±Concrete Curing SWMS
Curing of fresh concrete via water cure, membrane cure, or plastic sheet cure. Includes timing of cure start, β¦
π§±Concrete Pouring β Slab on Ground & Suspended SWMS
Concrete pouring covers placement of ready-mix concrete for slabs on ground, suspended slabs, footings, columnβ¦
π¨Floor Framing β Suspended Slab WAH SWMS
Floor framing on suspended slabs above 2 metres covers leading-edge fall protection, joist and bearer install,β¦
π¨Hard Strip Demolition SWMS
Hard strip demolition removing structural elements β concrete walls, slabs, brickwork, steel framing. Uses jacβ¦
π¨Painting Below 2m SWMS
Painting work below 2 metres covers ground-level interior and exterior painting, brush, roller and spray appliβ¦