Gantry Crane / Overhead Crane Operations SWMS
SWMS template for gantry crane / overhead crane operations. Covers EOT crane, bridge crane, pendant or radio control.. 8-state AU coverage, CIH-reviewed editable DOCX, available as an instant download.
SWMS variants reference your stateβs WHS legislation. Instant download after payment.
Gantry crane and overhead crane operations β including electric overhead travelling (EOT) cranes, bridge cranes, and pendant or radio-controlled units β are routinely deployed in fabrication workshops, warehouses, precast yards, and construction sites across Australia to lift, traverse, and lower loads above workers and plant. These operations are classified as High Risk Construction Work under WHS Regulation 2011 r291 wherever loads are suspended above persons or where structural collapse could occur, and they are listed activities under section 291 of the model WHS Regulations. A documented, signed-on Safe Work Method Statement is mandatory before work commences, must be reviewed when controls change or after any incident, and must be retained for the duration of the work plus two years where a notifiable incident occurs. This SWMS addresses crane pre-start inspection, lifting gear selection, exclusion zoning, communication protocols, and emergency lowering β aligned to AS 2550.1, AS 1418.1, and the Managing the Risk of Falling Objects Code of Practice.
Hazards identified
7 hazards covered, sorted by priority.
Fatal crush injuries, traumatic amputation, or multi-worker fatality from uncontrolled descent of load onto persons below
Severe head, chest, or pelvic trauma from lateral impact with loads exceeding several tonnes momentum
Catastrophic load release, hoist rope whip injury, and potential gantry beam collapse onto work area
Electrocution, arc flash burns, or cardiac arrest from contact with 415V three-phase supply
Load misplacement, crushing of riggers, or collision with structures causing secondary falling objects
Crushed fingers, degloving injuries, or amputation when hands are placed near moving rope or hook assemblies
Fractures, head injuries, or falls from height exceeding two metres requiring fall arrest engagement
Control measures
Hierarchy-of-controls order: elimination β substitution β isolation β engineering β administrative β PPE.
- 1Elimination β Eliminate manual handling under suspended loads by sequencing work so personnel are removed from the lift zone before hoisting commences, verified via exclusion zone walk.
- 2Elimination β Where feasible, replace overhead lifting with floor-level transfer systems, powered roller conveyors, or AGVs to remove the suspended load hazard entirely from the task.
- 3Substitution β Substitute manual pendant control with radio remote control on lifts exceeding 3 tonnes so the operator can stand clear of the load path and maintain optimal sight lines.
- 4Substitution β Substitute single-leg slings with engineered lifting beams or certified spreader bars for awkward loads to reduce sling angle stress and load instability during traverse.
- 5Engineering β Install audible travel alarms, strobe beacons, overload limiters, and upper/lower hoist limit switches on all cranes; verify function during the daily pre-start inspection per AS 2550.1.
- 6Engineering β Demarcate fixed exclusion zones beneath crane travel paths using floor-marked keep-clear zones, light curtains, or physical barricades preventing entry while load is airborne.
- 7Administrative β Only HRWL-licensed dogger (DG) and crane operator (CN/CV) personnel may rig and operate; verify licences, conduct documented pre-start, and brief lift plan at toolbox before each shift.
- 8Administrative β Implement standard AS 2550.1 hand signals and dedicated UHF channel for radio communication; nominate one signaller per lift and confirm via repeat-back protocol before motion.
- 9PPE β Mandatory hi-vis long sleeve, AS/NZS 1801 hard hat with chinstrap, AS/NZS 2210.3 safety boots, AS/NZS 1337.1 impact eyewear, and cut-5 rigging gloves when handling slings or chains.
- 10PPE β Issue AS/NZS 1891 compliant fall arrest harness with twin lanyard for any worker accessing crane walkways, gantry beams, or trolley maintenance platforms above two metres.
Applicable Codes of Practice
Mandates daily pre-start inspection, operator competency verification, exclusion zoning, and signalling protocols for all gantry and overhead crane operations.
Sets design, manufacture, and structural integrity duties including overload protection, limit switches, and rated capacity marking required during pre-use checks.
Triggers PCBU duty to implement exclusion zones, secondary retention, and tool tethering wherever objects or loads may fall from height during crane work.
Requires SWMS preparation, dogger (DG) and crane (CN/CV) licence verification, and notifiable incident reporting for suspended-load and struck-by work.
High-Risk Construction Work triggered
Access to crane walkways, gantry beams and trolley maintenance platforms above 2 metres during inspection and maintenance carries a fall risk.
Where the same crane work is carried out on a construction site it is construction work in an area with movement of powered mobile plant. In a fabrication shop, warehouse or precast yard the lifting is not construction work and the plant duties apply on their own.
PCBUs must prepare, consult workers on, and retain this SWMS for the duration of the work β penalties are substantial and indexed, with the current maximum following the prevailing WHS schedule.
Who this is for
- βFabrication and steel workshop supervisors operating EOT cranes
- βWarehouse and logistics managers running overhead bridge cranes
- βPrecast concrete yard riggers and crane operators
- βConstruction site doggers conducting workshop-fed lifts
What you receive
- βEditable DOCX template β Microsoft Word compatible
- βState-specific WHS legislation schedule (NSW/VIC/QLD/SA/WA/TAS/NT/ACT)
- βHazard register with risk ratings + hierarchy-of-control mapping
- βWorker sign-on register, pre-start checklist, and incident escalation flow
Worked example
At a mid-rise structural steel fabrication workshop in a regional industrial estate, the leading hand prints this SWMS and runs the pre-start brief at 6:45am before the day's column fabrication lifts. The dogger and EOT crane operator sign on after walking through the seven listed hazards, confirming their HRWL licences (DG and CN) are current and visible on the board. During the hazard walk, the operator identifies that the planned lift of a 4.2-tonne fabricated column will pass over the welding bays β referencing control item six, the team repositions floor-marked exclusion barricades and pauses the two welders until the load is landed. The signaller nominated for the shift confirms UHF channel 18 and runs a repeat-back test with the operator per control item eight. Mid-morning, a sling tag inspection reveals a frayed soft sling; work stops, the SWMS is reopened, and the team substitutes a certified spreader bar consistent with the engineered-beam control. The amendment is initialled on the SWMS sign-on sheet, all workers re-brief on the new rigging configuration, and the lift resumes. At shift end, the signed SWMS and amendment are filed in the site WHS register and retained per WHS record-keeping obligations.
Related legislation
- WHS Act 2011 (model)
- WHS Regulation 2025
- AS 2550 β Cranes hoists and winches; AS 1418 β Cranes including hoists and winches
Frequently asked questions
Is running an EOT crane in our workshop high risk construction work?
In a fabrication shop, warehouse or precast yard, no. That is not construction work, so section 291 and the section 299 SWMS duty do not attach to it. What does apply is the primary duty at section 19 of the WHS Act and the plant duties in the Regulation, which require a documented safe system of work for exactly this activity, and most principals will ask for the document regardless. Where the same crane work is carried out on a construction site, section 291 can engage: paragraph (o) where powered mobile plant is moving in the area, and paragraph (a) where workers access crane walkways or gantry beams above 2 metres.
What is two-blocking and how is it prevented?
Two-blocking is the hook block being drawn up hard against the trolley or sheave assembly while the hoist keeps pulling, which loads the wire rope beyond its rating and can part it with the load in the air. Prevention is an engineering control, not operator attention: upper and lower hoist limit switches, an overload limiter, and function verification during the daily pre-start rather than at the annual service. AS 1418.1 sets the rated capacity marking and overload protection duties for the crane itself, while AS 2550.1 governs the pre-start check that proves those devices still work today.
Who is allowed to rig and operate the crane?
A dogging licence is required where the person applies slinging techniques or directs the operator when the load is out of the operator line of sight, which covers most workshop lifts around structural sections and columns. The operator must be trained and competency-verified on the specific crane and control type rather than assumed competent from another machine. One signaller is nominated per lift, using the standardised hand signals in AS 2550.1 and a dedicated UHF channel with a repeat-back confirmation before any motion, because the common failure is two people signalling and the operator responding to whichever they saw first.
How do we stop people walking under a suspended load?
By making the lift path physically unavailable rather than relying on awareness. Fixed exclusion zones are demarcated beneath crane travel paths with floor-marked keep-clear zones, light curtains or barricades that prevent entry while the load is airborne, and work is sequenced so personnel are out of the zone before hoisting begins, verified by a walk. On lifts above 3 tonnes, radio remote control replaces pendant control so the operator stands clear of the load path with clear sight lines. The worked example shows a fabricated column path crossing welding bays, with barricades repositioned and the welders paused until the load lands.
What about maintenance access on the gantry itself?
That is a different hazard set and the document covers it separately. Access to crane walkways, gantry beams and trolley maintenance platforms above 2 metres requires a full body harness to AS/NZS 1891 with twin lanyards, and the climb itself carries slip and trip exposure on ladders and walkways. Electrically, contact with overhead busbars or a damaged pendant cable is the live risk, so isolation is proved before access rather than after. You receive an editable Word document, bought once, reviewed whenever controls change or after any incident and retained accordingly.
Document details
Related SWMS templates
π§Bridge Construction (General) SWMS
SWMS template for bridge construction (general). Covers Combines crane + steel + concrete + heights.. 8-state β¦
ποΈCrawler Crane Operations SWMS
SWMS template for crawler crane operations. Covers Lattice or telescopic crawler, ground prep, lift plan.. 8-sβ¦
βοΈAnodising Process Operations SWMS
SWMS template for anodising process operations. Covers Aluminium anodising, sulfuric/chromic acid lines.. 8-stβ¦
πΎApiary / Beekeeping Operations SWMS
SWMS template for apiary / beekeeping operations. Covers Hive inspection, honey extraction, apiary site work..β¦
πArticulated Dump Truck (ADT) Operations SWMS
SWMS template for articulated dump truck (adt) operations. Covers Bulk haulage on civil/mine. Tipping, reversiβ¦
πBackhoe Loader Operations SWMS
SWMS template for backhoe loader operations. Covers Combination digging + loading, reach radius, spotter.. 8-sβ¦