Intercom / Door Entry Systems SWMS
SWMS template for intercom / door entry systems. Covers Audio/video intercom install, multi-tenant systems.. 8-state AU coverage, CIH-reviewed editable DOCX, available as an instant download.
SWMS variants reference your state’s WHS legislation. Instant download after payment.
Installation and commissioning of intercom and door entry systems — including audio-only handsets, IP video intercoms, and multi-tenant directory systems in residential apartments, commercial foyers, and gated estates — involves a defined cluster of construction-phase electrical risks. Work typically combines low-voltage cabling, 230V power supply connections, ladder-based work at entry panels and ceiling-mounted distribution points, masonry and stud-wall penetrations, and integration with access control and door release hardware. Under WHS Regulation 2011 r291 and equivalent state regulations, electrical installation work performed as part of a construction project is High Risk Construction Work where it involves energised electrical installations, work at height exceeding 2m, or use of powered plant near live services. A documented Safe Work Method Statement is mandatory before work commences, must be developed in consultation with workers, kept accessible on site, and reviewed if controls fail or the work scope changes.
Hazards identified
7 hazards covered, sorted by priority.
Electric shock, cardiac arrhythmia, deep-tissue burns, fall from ladder following involuntary muscular reaction, potential fatality
Fractures, head injury, spinal injury from unstable ladder setup on uneven foyer thresholds or paved driveways
Electric shock from energised cable strike, water damage from plumbing strike, gas release causing fire or asphyxiation
Acute respiratory irritation and long-term risk of silicosis, accelerated COPD, and silica-related lung cancer
Lumbar strain, crush injuries to fingers, shoulder impingement from awkward postures in tight foyer cupboards
Flash burns to face and hands, retinal damage, hearing damage, ignition of nearby combustibles in riser cupboards
Assault, theft of tools causing rushed work, vehicle strike at driveway entry panels, no immediate first-aid response
Control measures
Hierarchy-of-controls order: elimination → substitution → isolation → engineering → administrative → PPE.
- 1Elimination — Where practicable, pre-fabricate and bench-terminate PSU, backbox wiring loom and door-station tails off-site so live work at the wall is eliminated entirely.
- 2Elimination — Schedule drilling and core penetrations before energisation of the final sub-circuit so all cabling work occurs on a fully de-energised installation.
- 3Substitution — Substitute hammer-drilling of masonry with diamond core drilling using on-tool water suppression to remove impact-driven dust generation at the source.
- 4Substitution — Replace standard A-frame ladders with a podium step or low-level mobile scaffold for entry-panel heights above 1.8m to provide a stable working platform.
- 5Engineering — Isolate, lock-out and tag the final sub-circuit feeding the intercom PSU at the distribution board and verify dead with a tested two-pole voltage indicator before work.
- 6Engineering — Use a cable and pipe detector (AS/NZS 4836 compliant device) to scan all drilling locations and mark concealed services before penetrating any wall or slab.
- 7Engineering — Fit RCD protection (≤30mA) on all portable tool supply leads and inspect leads under the AS/NZS 3012 site-testing regime before each shift.
- 8Administrative — Conduct daily pre-start briefing using this SWMS, sign-on register, and verify electrical licence and EWP/ladder competency for each worker on task.
- 9Administrative — Establish exclusion zone with bollards and signage at foyer/driveway entry panels and notify building manager so residents are diverted during work.
- 10PPE — Wear Cat 2 arc-rated long sleeves, AS/NZS 1337 safety eyewear, P2 respirator during drilling, AS/NZS 2210 safety footwear, and Class 0 insulated gloves for any live verification.
Applicable Codes of Practice
Mandates isolation, polarity verification, and earthing requirements when terminating the 230V supply to intercom PSU and door release hardware.
Requires RCD protection, lead testing/tagging, and safe distribution arrangements for portable tools used during intercom rough-in and fit-off.
Sets out PCBU duty to isolate, test-for-dead, and use only licensed electrical workers when working on or near energised parts of the intercom circuit.
Triggers selection of platform over ladder, edge-protection assessment, and competency verification for entry-panel installs above 2m working height.
High-Risk Construction Work triggered
Final termination of the 230V PSU and integration with door release relays occurs on or adjacent to the energised building distribution system.
Mounting of entry panels, ceiling-mounted hub units and riser cabling regularly requires ladder or platform work above the 2m fall threshold.
Drilling masonry and stud walls in older apartment foyers can intersect concealed gas risers, requiring service location before penetration.
PCBU must prepare the SWMS before work starts, consult affected workers, keep it accessible on site, and retain it for at least two years after any notifiable incident; penalties are substantial and indexed, with the current maximum following the prevailing WHS schedule.
Who this is for
- →Licensed electricians installing residential and commercial intercoms
- →Security and communications contractors on multi-tenant apartment projects
- →Principal contractors coordinating Tier 2 fit-out electrical trades
- →Self-employed data/comms technicians performing entry-system upgrades
What you receive
- ✓Editable DOCX template — Microsoft Word compatible
- ✓State-specific WHS legislation schedule (NSW/VIC/QLD/SA/WA/TAS/NT/ACT)
- ✓Hazard register with risk ratings + hierarchy-of-control mapping
- ✓Worker sign-on register, pre-start checklist, and incident escalation flow
Worked example
On a 42-unit apartment refurbishment, the lead electrician opens this SWMS at the 7am pre-start with two technicians and the building manager in the ground-floor foyer. They walk the scope: replace the existing audio handset system with an IP video intercom, mount a new directory panel at the street entry, run Cat6 back to the comms riser, and integrate with the existing electric strike. Working through the hazard register, the team flags that the PSU sub-circuit at the riser board must be isolated, locked and tagged before any termination — the lead applies his personal danger tag and tests-for-dead with a two-pole tester noted in the SWMS. For the street panel at 1.9m, the SWMS triggers selection of a podium step rather than the A-frame originally loaded on the van, because the threshold paving is uneven. A cable detector scan of the masonry penetration point identifies an unmapped conduit; the SWMS control to re-mark and re-scan is followed, and the drill point is shifted 200mm. All three workers sign the consultation register. Mid-morning, a resident wheels a pram through the work zone — the supervisor halts work, repositions the bollards per the exclusion-zone control, and adds a note to the SWMS review log so the same gap is closed on the remaining 41 doors.
Related legislation
- WHS Act 2011 (model)
- WHS Regulation 2025
- AS/NZS 3000 — Electrical installations; AS/NZS 3012 — Electrical installations construction sites
Frequently asked questions
Do I need a SWMS for an intercom upgrade in an occupied apartment building?
Yes. Terminating the 230 V supply to the intercom PSU and integrating with door release relays is work on or near energised electrical installations or services — section 291(k) of the WHS Regulation 2025 — and mounting entry panels, ceiling hub units and riser cabling regularly puts workers above the 2 m fall threshold, which is section 291(a). Where a masonry penetration in an older foyer runs near a concealed gas riser, section 291(i) can apply as well. Section 299 requires the SWMS be prepared before work starts, developed with the workers, kept accessible on site, and reviewed if a control fails or the scope changes.
Does this cover masonry drilling for the entry panel and the silica dust?
Yes, on both fronts. The dust control is a substitution rather than a mask-first approach: diamond core drilling with on-tool water suppression replaces hammer drilling so the dust is never generated, with a P2 respirator and eye protection behind it. Before any hole is started, every drilling location is scanned with a cable and pipe detector and the services marked — a strike on an energised cable, a water line or a gas riser is why that scan is a hold point rather than a courtesy. Where the scan finds an unmapped conduit, the method is to re-mark, re-scan and shift the drill point.
How does the SWMS handle residents and public walking through the work zone?
It makes the exclusion zone a named control rather than an afterthought. Bollards and signage go up at the foyer or driveway entry panel, the building manager is notified so residents can be diverted, and the zone is re-set whenever the work position moves. That matters because entry panels sit exactly where a pram, a delivery or a reversing vehicle comes through, and a technician on a podium step has no way to react. The lone-working hazard is carried too: an unsecured entry with public access, no immediate first-aid response, and the pressure to rush that comes with tool theft.
Does one document cover both the extra-low voltage cabling and the 230 V side?
Yes — the method runs the whole scope, from Cat6 back to the comms riser through to the PSU termination and the door release integration. What it does not do is change who may perform each part: the 230 V termination and any live verification is licensed electrical work, and the SWMS records that as a competency control with the licence check built into the daily pre-start sign-on. Portable tools used on the job fall under the AS/NZS 3012 site regime, meaning RCD protection at 30 mA or less on supply leads and lead inspection before each shift.
Can one SWMS cover a whole building, or do I need one per door?
One document covers the scope of work rather than a single door — on a 42-unit refurbishment you brief it once, sign the crew on, then keep it live as the job moves through the building. The review log is what makes that work: when a resident walks through the work zone and the bollard position turns out to be wrong, the correction is noted and the same gap is closed on the remaining doors instead of being rediscovered at each one. You buy an editable Word document once and reuse it across the project, adding the actual panel locations, isolation points and access arrangements before each stage.
Document details
Related SWMS templates
🏢Office Furniture / Workstation Install SWMS
SWMS template for office furniture / workstation install. Covers Modular furniture, workstation systems.. 8-st…
❄️VRV / VRF System Install (Multi-Head) SWMS
SWMS template for vrv / vrf system install (multi-head). Covers Outdoor unit, multiple indoor heads, refrigera…
🏠Acoustic Soundproofing / Sound Insulation SWMS
SWMS template for acoustic soundproofing / sound insulation. Covers Theatre, studio, party-wall acoustic syste…
🏠Acrylic Render Application SWMS
SWMS template for acrylic render application. Covers Modern texture coats, Rockcote/Dulux AcraTex systems.. 8-…
⚙️Boiler Maintenance / Inspection SWMS
SWMS template for boiler maintenance / inspection. Covers Drum/tube entry, valve overhaul, refractory.. 8-stat…
🏚️Box Gutter Installation SWMS
SWMS template for box gutter installation. Covers Box gutter tray, sumps, overflow. 8-state AU coverage, CIH-r…