Crawler Crane Operations SWMS
SWMS template for crawler crane operations. Covers Lattice or telescopic crawler, ground prep, lift plan.. 8-state AU coverage, CIH-reviewed editable DOCX, available as an instant download.
SWMS variants reference your stateβs WHS legislation. Instant download after payment.
Crawler crane operations involve the deployment, set-up and use of lattice or telescopic boom crawler cranes for heavy lifting on civil, infrastructure and commercial construction sites. The work routinely involves lifts exceeding the duty chart on uneven or made ground, slewing of suspended loads near workers and structures, and travel of the crane under load β each of which is classified as High Risk Construction Work under WHS Regulation 2011 r291(g) (risk of falling object), r291(h) (powered mobile plant) and r291(p) (tilt-up/precast erection where applicable). A Safe Work Method Statement is mandatory before this work commences and must be prepared in consultation with operators, dogmen, riggers and the principal contractor under WHS Act s47. The SWMS must document the lift plan, ground bearing assessment, exclusion zones and emergency procedures, and be kept available for inspection for the duration of the high risk construction work, then retained for at least two years (longer if a notifiable incident occurs).
Hazards identified
7 hazards covered, sorted by priority.
Crane overturn under load causing crushing fatalities, dropped load, structural collapse and prosecution under WHS Act s31 reckless conduct
Boom buckling, two-block failure or tip-over with fatal crush injuries to riggers and adjacent workers within fall radius
Electrocution of operator and ground crew, arc flash burns, plant fire and breach of ESV/Energex no-go zone clearances
Fatal crush injuries to dogmen, riggers or third parties caught between counterweight and fixed structures or vehicles
Load contact with workers or structure, rigging failure, dropped object and serious crush or laceration injuries
Sudden load release at height causing fatal impact injuries and prosecution for failure to inspect lifting gear under r213
Misinterpreted signals, mispositioned load, secondary collisions and category 2 offence exposure for the PCBU
Control measures
Hierarchy-of-controls order: elimination β substitution β isolation β engineering β administrative β PPE.
- 1Elimination β Where feasible, prefabricate and lift modules at ground level or use mobile tower cranes with fixed bases to eliminate crawler travel under load on suspect ground.
- 2Elimination β Reschedule lifts outside forecast wind windows above 9.6 m/s at the hook and cease operations when lightning is within 10 km per AS 1418.5 Appendix C.
- 3Substitution β Substitute a larger duty crawler so the planned lift sits below 75% of rated capacity at maximum radius, removing critical-lift classification under AS 2550.1.
- 4Substitution β Replace single-point picks with engineered lifting beams and certified rigging frames to substitute uncontrolled load geometry with a fixed, calculated configuration.
- 5Engineering β Install certified crane mats or steel road plates sized to the bearing pressure calculation in the lift study, signed by a competent ground engineer per AS 2550.1 clause 6.4.
- 6Engineering β Operate cranes only with functioning rated capacity indicator, anti-two-block and load moment limiter calibrated within 12 months and logged in the plant logbook.
- 7Administrative β Implement a documented lift plan signed by the crane supervisor, rigger and PCBU representative before each non-routine lift in accordance with the Tower and Mobile Crane CoP.
- 8Administrative β Establish a hard-barricaded exclusion zone covering the full slew radius plus load drop zone, controlled by a dedicated spotter with two-way radio on a dedicated channel.
- 9PPE β Issue and enforce high-visibility long-sleeve garments to AS/NZS 4602.1, Class 2 hard hats to AS/NZS 1801, steel-cap boots to AS/NZS 2210.3 and cut-resistant rigging gloves.
- 10PPE β Provide impact-rated safety eyewear to AS/NZS 1337.1 and Class 5 hearing protection for ground crew within 7 m of the diesel power pack during sustained operations.
Applicable Codes of Practice
Crawler crane lifting triggers r291(g) and r291(h), mandating a SWMS prepared, communicated and available on site before work commences.
Sets ground bearing assessment, duty chart compliance, pre-start inspection and exclusion zone requirements directly referenced in the lift plan.
Provides the regulator-endorsed method for assembly, lift planning, dogging communication and de-commissioning incorporated into the SWMS control measures.
Defines wind speed limits, structural integrity testing and rated capacity calculations the operator must verify before each lift cycle.
High-Risk Construction Work triggered
A crawler crane is powered mobile plant operating with slew, travel and lifting motions among workers, directly engaging Schedule 1 item 13 criteria.
Where the crawler erects precast panels, columns or bridge beams, the lift activity meets the precast erection trigger requiring the SWMS.
Riggers accessing the boom, counterweight assembly or load landing points typically work above 2 m, capturing the fall risk category.
PCBUs must prepare the SWMS in consultation with workers, supply it before work starts and retain it for at least two years; penalties are substantial and indexed, with the current maximum following the prevailing WHS schedule.
Who this is for
- βCrane hire companies supplying crawler plant to civil contractors
- βPrincipal contractors on infrastructure and bridge projects
- βLift supervisors and dogman/rigger crews on precast erection
- βCrane operators holding CN/C6 high risk work licences
What you receive
- βEditable DOCX template β Microsoft Word compatible
- βState-specific WHS legislation schedule (NSW/VIC/QLD/SA/WA/TAS/NT/ACT)
- βHazard register with risk ratings + hierarchy-of-control mapping
- βWorker sign-on register, pre-start checklist, and incident escalation flow
Worked example
On a regional water treatment upgrade, the lift supervisor opens the Crawler Crane Operations SWMS at the 6:30 am pre-start brief in the site shed. A 180-tonne lattice crawler is scheduled to set a 28-tonne sedimentation tank module at 22 m radius β 71% of rated capacity. Working through the SWMS hazard register, the dogman flags that overnight rain has saturated the southern pad. The crew references control 5 (engineered crane mats with bearing pressure calculation) and the supervisor pauses the lift until the geotech contractor re-tests the pad and re-signs the lift plan. The SWMS exclusion zone diagram is marked up on the site plan and a second spotter is added to cover the slew tail swing near the temporary site office, satisfying control 8. Each worker signs the SWMS sign-on register, confirming they have been consulted under WHS Act s47. Mid-lift, wind at the hook anemometer reaches 8.4 m/s and is climbing. The dogman calls a hold on the dedicated radio channel, the operator boom-up parks the load, and the team re-reads the SWMS wind threshold (9.6 m/s). The lift resumes only when the three-minute average drops, with the adjustment noted on the SWMS as a field amendment and countersigned, ready for regulator inspection.
Related legislation
- WHS Act 2011 (model)
- WHS Regulation 2025
- AS 2550 β Cranes, hoists and winches; AS 1418 series