OH Consultant
← All SWMS Documents
πŸ—οΈ

HIAB & Truck Loader Crane Operations SWMS

HIAB knuckle-boom and truck-mounted loader crane operations β€” crane set-up, outrigger deployment, lift planning, load chart compliance, and exclusion zone management during deliveries and civil works.

βš–οΈWHS Regulation 2025 & Codes of Practice β€” legally binding from 1 July 2026 (s26A)
πŸ‘·Reviewed by certified occupational health and safety professionals
πŸ—ΊοΈState-specific variants for all 8 Australian jurisdictions
$199 AUDβœ“ Instant Download Available

SWMS variants reference your state’s WHS legislation. Instant download after payment.

HIAB and truck-mounted loader crane operations involve articulated knuckle-boom cranes mounted on rigid or semi-trailer chassis, used to load, unload, and place materials at construction sites, civil works, and material yards across Australia. The work combines mobile plant operation, slewing crane lifting, and roadside delivery β€” frequently in live traffic corridors or alongside pedestrians and other trades. Under WHS Regulation 2025 r.291, a Safe Work Method Statement is mandatory because the work is high-risk construction work involving loads suspended over people (Schedule 3 Cat. 4) and structural failure risk from outrigger ground-bearing pressure (Cat. 5). Operators must hold a current HRW licence (C0, C2 or CN depending on capacity and slew configuration) under r.162, and the crane must comply with AS 2549:2004 Cranes β€” Vehicle Loading. This SWMS documents lift planning, outrigger deployment, load chart verification, exclusion zone control, and rigging duties required before any lift commences.

Hazards identified

7 hazards covered, sorted by priority.

Outrigger punch-through on soft, filled, or unconsolidated groundHIGH

Catastrophic crane overturn, crushing injuries to ground crew, structural collapse onto adjacent property or public footpath

Load drop from incorrectly rigged or unbalanced suspended packHIGH

Fatal crush injuries, fractured limbs, damaged underground services or finished structures below the lift path

Overload exceeding load chart radius/angle ratingHIGH

Boom structural failure, hydraulic ram rupture, crane tip-over with fatal consequences for operator and bystanders

Contact with overhead powerlines during boom slew or extensionHIGH

Electrocution of operator and dogger, arc-flash burns, induced current to load and rigging gear

Persons entering the exclusion zone beneath suspended loadsHIGH

Fatal crush injury from dropped load, struck-by from swinging load, statutory breach of HRCW Cat. 4 duty

Traffic interaction during roadside kerbside deliveriesMEDIUM

Vehicle strike to crew, crane outrigger struck by passing traffic, traffic incident with public liability exposure

Pinch and crush points at slew bearing, stabiliser legs, and folding boom sectionsMEDIUM

Amputation of fingers, crush injuries to hands and feet during deployment, stow, and rigging operations

Control measures

Hierarchy-of-controls order: elimination β†’ substitution β†’ isolation β†’ engineering β†’ administrative β†’ PPE.

  1. 1Elimination β€” Where practicable, schedule deliveries directly to ground-level laydown areas eliminating the need to lift over occupied structures, scaffolds, or active work zones below.
  2. 2Elimination β€” Refuse the lift and reschedule if ground conditions, wind speed above manufacturer limits, or overhead service clearances cannot be verified before set-up.
  3. 3Substitution β€” Substitute manual sling rigging with engineered lifting frames, vacuum lifters, or proprietary brick/block clamps rated and tagged to AS 4991:2004 for the load type.
  4. 4Engineering β€” Deploy all outriggers fully extended onto timber or engineered bog mats sized per ground-bearing pressure calculation in the lift study; verify chassis level within manufacturer tolerance.
  5. 5Engineering β€” Use load moment indicator (LMI) and rated capacity limiter functional per AS 2549:2004 cl.2.9; do not bypass cut-outs or override anti-two-block devices.
  6. 6Administrative β€” Complete a documented lift plan referencing the load chart, radius, boom angle, and rigging configuration before each non-routine lift; dogger and operator sign-on.
  7. 7Administrative β€” Establish and barricade an exclusion zone equal to the lift radius plus load dimension; post spotters and use clear hand signals or UHF channel per AS 2550.1.
  8. 8Administrative β€” Verify operator HRW C0/C2/CN licence under r.162 and dogger DG licence; confirm currency before site entry and record on the daily prestart.
  9. 9PPE β€” Hi-vis Class D/N garments to AS/NZS 4602.1, AS/NZS 1801 hard hat, AS/NZS 2210.3 safety footwear with metatarsal protection, and AS/NZS 2161.3 cut-resistant rigging gloves.
  10. 10PPE β€” UV-rated safety eyewear to AS/NZS 1337.1 and Class 5 hearing protection to AS/NZS 1270 when working near hydraulic power packs and traffic noise above 85 dB(A).

Applicable Codes of Practice

AS 2550.1:2011 Cranes, hoists and winches β€” Safe use β€” General requirementsβš– Legally binding Β· 1 Jul 2026

Mandates pre-operational checks, exclusion zones, signalling, and operator competency β€” directly triggered for every HIAB lift cycle and dogger interface.

AS 2549:2004 Cranes β€” Vehicle Loadingβš– Legally binding Β· 1 Jul 2026

Sets design, stability, load chart display, and LMI requirements specific to truck-mounted loader cranes; non-compliance invalidates the lift.

Model Code of Practice β€” Managing the Risks of Plant in the Workplace (SWA 2024)βš– Legally binding Β· 1 Jul 2026

Imports r.203–r.214 duties on guarding, isolation, maintenance, and competency assessment applicable to mobile crane plant operations.

AS 4991:2004 Lifting Devices

Governs slings, shackles, chains and lifting attachments β€” requires WLL marking, inspection register, and removal from service criteria for all rigging used.

High-Risk Construction Work triggered

4
Work involving a risk of a person falling more than 2m or loads suspended over people

HIAB lifts routinely pass loads over delivery yards, footpaths, and adjacent trades β€” the suspended load over people criterion is triggered at every site.

5
Work involving structural alterations or repairs that require temporary support

Outrigger ground-bearing loads can exceed 15 tonnes per pad β€” structural failure of pavement, slab edge, or fill triggers Cat. 5 temporary support risk.

Legal consequence

PCBU must prepare, consult workers on, and retain this SWMS for the duration of the high-risk construction work; penalties for non-compliance are substantial and indexed annually under the prevailing WHS schedule.

Who this is for

  • β†’HIAB and truck-mounted crane operators across civil and construction
  • β†’Material delivery and transport supervisors on building sites
  • β†’Crane hire company schedulers and lift planners
  • β†’Principal contractor site managers receiving crane deliveries

What you receive

  • βœ“Editable DOCX template β€” Microsoft Word compatible
  • βœ“State-specific WHS legislation schedule (NSW/VIC/QLD/SA/WA/TAS/NT/ACT)
  • βœ“Hazard register with risk ratings + hierarchy-of-control mapping
  • βœ“Worker sign-on register, pre-start checklist, and incident escalation flow

Worked example

On a suburban townhouse civil project, a precast panel delivery arrives kerbside on a residential street. The HIAB operator opens this SWMS at the truck cab before deploying outriggers. At the toolbox brief with the site supervisor and dogger, they walk through the hazard register β€” identifying soft verge ground on the driver's side, a Telstra aerial cable 6 metres overhead, and pedestrian footpath traffic. Using the SWMS controls, they select 600 Γ— 600 mm timber bog mats under the verge-side outriggers per the engineering control, mark out a 9-metre exclusion zone with bunting and witches hats, and station a traffic spotter under the administrative control. The operator confirms his HRW C2 licence and the dogger's DG ticket on the prestart sign-on sheet attached to the SWMS. Mid-lift, a pedestrian approaches the exclusion zone β€” the spotter halts the slew immediately, the operator parks the load, and the SWMS clause requiring lift suspension on zone breach is followed. Once the footpath clears, the lift resumes under the documented signalling protocol. After completion, the dogger inspects the slings against AS 4991, notes a damaged shackle for removal, and the supervisor countersigns the SWMS as evidence of consultation and compliance with WHS r.291.

Related legislation

  • WHS Act 2011 (model)
  • WHS Regulation 2025
  • AS 2550 β€” Cranes hoists and winches; AS 1418 β€” Cranes including hoists and winches
What's in this SWMS

Document details

Regulation
WHS Regulation 2025 (all states) r.162 β€” HRW Licence C0/C2 (slewing mobile crane); AS 2549:2004 Vehicle Loading Cranes; Heavy Vehicle National Law
HRCW Category
HRCW Cat. 4: Loads suspended over people; Cat. 5: Structural failure risk from outrigger loads
Hazards Identified
12 hazards with controls
Format
Editable DOCX (Microsoft Word)
Author
Certified Industrial Hygienist (CIH)
Delivery
Instant download after payment