HIAB & Truck Loader Crane Operations SWMS
HIAB knuckle-boom and truck-mounted loader crane operations β crane set-up, outrigger deployment, lift planning, load chart compliance, and exclusion zone management during deliveries and civil works.
SWMS variants reference your stateβs WHS legislation. Instant download after payment.
HIAB and truck-mounted loader crane operations involve articulated knuckle-boom cranes mounted on rigid or semi-trailer chassis, used to load, unload, and place materials at construction sites, civil works, and material yards across Australia. The work combines mobile plant operation, slewing crane lifting, and roadside delivery β frequently in live traffic corridors or alongside pedestrians and other trades. Under WHS Regulation 2025 r.291, a Safe Work Method Statement is mandatory because the work is high-risk construction work involving loads suspended over people (Schedule 3 Cat. 4) and structural failure risk from outrigger ground-bearing pressure (Cat. 5). Operators must hold a current HRW licence (C0, C2 or CN depending on capacity and slew configuration) under r.162, and the crane must comply with AS 2549:2004 Cranes β Vehicle Loading. This SWMS documents lift planning, outrigger deployment, load chart verification, exclusion zone control, and rigging duties required before any lift commences.
Hazards identified
7 hazards covered, sorted by priority.
Catastrophic crane overturn, crushing injuries to ground crew, structural collapse onto adjacent property or public footpath
Fatal crush injuries, fractured limbs, damaged underground services or finished structures below the lift path
Boom structural failure, hydraulic ram rupture, crane tip-over with fatal consequences for operator and bystanders
Electrocution of operator and dogger, arc-flash burns, induced current to load and rigging gear
Fatal crush injury from dropped load, struck-by from swinging load, statutory breach of HRCW Cat. 4 duty
Vehicle strike to crew, crane outrigger struck by passing traffic, traffic incident with public liability exposure
Amputation of fingers, crush injuries to hands and feet during deployment, stow, and rigging operations
Control measures
Hierarchy-of-controls order: elimination β substitution β isolation β engineering β administrative β PPE.
- 1Elimination β Where practicable, schedule deliveries directly to ground-level laydown areas eliminating the need to lift over occupied structures, scaffolds, or active work zones below.
- 2Elimination β Refuse the lift and reschedule if ground conditions, wind speed above manufacturer limits, or overhead service clearances cannot be verified before set-up.
- 3Substitution β Substitute manual sling rigging with engineered lifting frames, vacuum lifters, or proprietary brick/block clamps rated and tagged to AS 4991:2004 for the load type.
- 4Engineering β Deploy all outriggers fully extended onto timber or engineered bog mats sized per ground-bearing pressure calculation in the lift study; verify chassis level within manufacturer tolerance.
- 5Engineering β Use load moment indicator (LMI) and rated capacity limiter functional per AS 2549:2004 cl.2.9; do not bypass cut-outs or override anti-two-block devices.
- 6Administrative β Complete a documented lift plan referencing the load chart, radius, boom angle, and rigging configuration before each non-routine lift; dogger and operator sign-on.
- 7Administrative β Establish and barricade an exclusion zone equal to the lift radius plus load dimension; post spotters and use clear hand signals or UHF channel per AS 2550.1.
- 8Administrative β Verify operator HRW C0/C2/CN licence under r.162 and dogger DG licence; confirm currency before site entry and record on the daily prestart.
- 9PPE β Hi-vis Class D/N garments to AS/NZS 4602.1, AS/NZS 1801 hard hat, AS/NZS 2210.3 safety footwear with metatarsal protection, and AS/NZS 2161.3 cut-resistant rigging gloves.
- 10PPE β UV-rated safety eyewear to AS/NZS 1337.1 and Class 5 hearing protection to AS/NZS 1270 when working near hydraulic power packs and traffic noise above 85 dB(A).
Applicable Codes of Practice
Mandates pre-operational checks, exclusion zones, signalling, and operator competency β directly triggered for every HIAB lift cycle and dogger interface.
Sets design, stability, load chart display, and LMI requirements specific to truck-mounted loader cranes; non-compliance invalidates the lift.
Imports r.203βr.214 duties on guarding, isolation, maintenance, and competency assessment applicable to mobile crane plant operations.
Governs slings, shackles, chains and lifting attachments β requires WLL marking, inspection register, and removal from service criteria for all rigging used.
High-Risk Construction Work triggered
HIAB lifts routinely pass loads over delivery yards, footpaths, and adjacent trades β the suspended load over people criterion is triggered at every site.
Outrigger ground-bearing loads can exceed 15 tonnes per pad β structural failure of pavement, slab edge, or fill triggers Cat. 5 temporary support risk.
PCBU must prepare, consult workers on, and retain this SWMS for the duration of the high-risk construction work; penalties for non-compliance are substantial and indexed annually under the prevailing WHS schedule.
Who this is for
- βHIAB and truck-mounted crane operators across civil and construction
- βMaterial delivery and transport supervisors on building sites
- βCrane hire company schedulers and lift planners
- βPrincipal contractor site managers receiving crane deliveries
What you receive
- βEditable DOCX template β Microsoft Word compatible
- βState-specific WHS legislation schedule (NSW/VIC/QLD/SA/WA/TAS/NT/ACT)
- βHazard register with risk ratings + hierarchy-of-control mapping
- βWorker sign-on register, pre-start checklist, and incident escalation flow
Worked example
On a suburban townhouse civil project, a precast panel delivery arrives kerbside on a residential street. The HIAB operator opens this SWMS at the truck cab before deploying outriggers. At the toolbox brief with the site supervisor and dogger, they walk through the hazard register β identifying soft verge ground on the driver's side, a Telstra aerial cable 6 metres overhead, and pedestrian footpath traffic. Using the SWMS controls, they select 600 Γ 600 mm timber bog mats under the verge-side outriggers per the engineering control, mark out a 9-metre exclusion zone with bunting and witches hats, and station a traffic spotter under the administrative control. The operator confirms his HRW C2 licence and the dogger's DG ticket on the prestart sign-on sheet attached to the SWMS. Mid-lift, a pedestrian approaches the exclusion zone β the spotter halts the slew immediately, the operator parks the load, and the SWMS clause requiring lift suspension on zone breach is followed. Once the footpath clears, the lift resumes under the documented signalling protocol. After completion, the dogger inspects the slings against AS 4991, notes a damaged shackle for removal, and the supervisor countersigns the SWMS as evidence of consultation and compliance with WHS r.291.
Related legislation
- WHS Act 2011 (model)
- WHS Regulation 2025
- AS 2550 β Cranes hoists and winches; AS 1418 β Cranes including hoists and winches
Frequently asked questions
We are only dropping off materials. Does a HIAB delivery really need a SWMS?
Yes, once the truck sets up on or beside a construction site. The lift happens in an area where powered mobile plant is moving, paragraph (o) of section 291, and kerbside deliveries put the work on or adjacent to a road in use by traffic, paragraph (n). Where the boom can slew or extend within the minimum approach distance of overhead lines, paragraph (k) applies as well. Section 299 then requires the SWMS before work commences. The delivery framing is exactly what causes the gap: the truck is treated as transport until the outriggers come down, and by then the lift has already started.
How do I know the outriggers will not punch through?
By calculating rather than eyeballing it. Pad loads on a loader crane can exceed 15 tonnes per outrigger, concentrated on a footprint the size of a dinner plate, which is far beyond what a verge, a service trench backfill, a slab edge or recent fill will carry. All outriggers go to full extension onto timber or engineered bog mats sized from the ground-bearing pressure calculation in the lift study, and chassis level is confirmed within the manufacturer tolerance before the boom moves. In the worked example the crew mats only the verge-side legs after identifying soft ground on one side of the truck.
Can the operator override the load moment indicator to finish a lift?
No. The load moment indicator and rated capacity limiter must be functional in line with AS 2549:2004, and the method prohibits bypassing cut-outs or overriding anti-two-block devices. The reason operators reach for the override is a misread chart rather than a genuine fault: capacity on a knuckle boom is a function of radius and boom angle, so extending out to reach past an obstruction cuts the rating even though the pack on the hook has not changed weight. The lift plan records the chart figure, radius, boom angle and rigging configuration before the lift, so the limiter confirms a decision already made.
What licences do the operator and the dogger need?
The operator holds a current high risk work licence under regulation 162, with the class matched to the crane capacity and slew configuration rather than to the truck. Where the load or its travel path leaves the operator line of sight, a licensed dogger directs the lift and holds a current dogging licence. Both are verified for currency before site entry and recorded on the daily pre-start alongside the sign-on, because the licence check is the item most often skipped when a delivery arrives outside the normal induction window and the site is waiting on the materials.
Does it cover deliveries onto a live street with pedestrians about?
Yes, that is the scenario it is built around. The exclusion zone is set at the lift radius plus the load dimension, barricaded rather than coned, with spotters posted and communication on standardised hand signals or a nominated UHF channel per AS 2550.1. Footpath and traffic interaction gets its own control through the traffic management arrangement. The worked example is a kerbside precast delivery on a residential street with an aerial cable roughly 6 metres overhead, soft verge on one side and a public footpath in the drop zone. You receive an editable Word document, bought once, that you complete with the actual setup position.
Document details
Related SWMS templates
πTruck-Mounted Crane SWMS
Operation of truck-mounted articulating crane (Hiab / Palfinger) for material delivery and lifting. HRWL CN orβ¦
ποΈMobile Crane Lifts SWMS
Franna, city crane, slewing mobile crane and hydraulic truck-crane operations β lift-plan development, outriggβ¦
ποΈPre-cast Tilt-up Panels SWMS
Pre-cast tilt-up concrete panel erection covers crane lift planning, lifting insert engineering, propping scheβ¦
πCrane & Lifting JSA SWMS
This template covers mobile crane lifting operations β slewing and non-slewing mobile cranes and vehicle loadiβ¦
πTipper Truck SWMS
Tipper and dump truck operations on civil and mining sites β pre-start checks, tipping area inspections, over-β¦
ποΈTower Crane Operations SWMS
Tower crane erection oversight, daily pre-start inspection, lifting operations, blind-lift management, slew anβ¦